3750 S WILTON PL 90018
Certificate Information: 3750 S WILTON PL 90018
- Application / Permit
- 23014-10000-04949
- Plan Check / Job No.
- B23LA22794
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 624 SQUARE FEET 2 STORY DETACHED ADU PER ORDINANCE
- Permit Issued
- Issued on 6/17/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2023 | JOHN MESIAS |
| Corrections Issued | 12/22/2023 | JOHN MESIAS |
| Quality Review Completed | 1/3/2024 | KESETE HAREGOT |
| Building Plans Picked Up | 1/9/2024 | APPLICANT |
| Applicant returned to address corrections | 5/13/2024 | JOHN MESIAS |
| Plan Check Approved | 5/28/2024 | JOHN MESIAS |
| Issued | 6/17/2024 | APPLICANT |
| CofO in Progress | 11/25/2025 | SABAS ALONSO |
| Permit Finaled | 11/25/2025 | DEROLD HAUFF |
| CofO Issued | 11/25/2025 | DEROLD HAUFF |
| Permit Finaled | 11/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2024 | CHRISTINA BRACO |
| Address approval | Cleared | 2/28/2024 | ARNULFO CHAMU |
| Low Impact Development (LID) | Cleared | 3/22/2024 | MITESH PATEL |
| Construction near power lines | Cleared | 5/6/2024 | RIDWAN HARDY |
| Sewer availability | Cleared | 5/13/2024 | MATIAS FARFAN |
| Roof/Waste drainage to street | Cleared | 5/16/2024 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/8/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/8/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 7/9/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2024 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 8/20/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 8/27/2024 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 8/30/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 9/20/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 9/20/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 9/20/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/7/2025 | Not Ready for Inspection | BARRY HACHE |
| Interior/Exterior Lathing | 4/7/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 4/10/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/10/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/14/2025 | Approved | SABAS ALONSO |
| Shower Pan | 4/14/2025 | Approved | SABAS ALONSO |
| Insulation | 4/16/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 4/21/2025 | Approved | ANTHONY RAMOS |
| Green Building Final | 6/12/2025 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 6/12/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | SABAS ALONSO |
| Sewer | 6/12/2025 | Approved | SABAS ALONSO |
| Smoke Detectors | 6/12/2025 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 6/12/2025 | Approved | SABAS ALONSO |
| Final | 6/17/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 6/17/2025 | Approved | SABAS ALONSO |
| Service/Power Release | 6/17/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 6/17/2025 | Approved | SABAS ALONSO |
| Final | 7/3/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 7/25/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 8/14/2025 | Corrections Issued | SABAS ALONSO |
| Final | 11/20/2025 | Corrections Issued | SABAS ALONSO |
| Final | 11/24/2025 | OK to Issue CofO | SABAS ALONSO |