527 W 90TH ST 90044

Certificate Information: 527 W 90TH ST 90044

Application / Permit
23014-10000-04944
Plan Check / Job No.
B23LA22242
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan BUILDING UNIT (#2): INTERIOR REMODEL OF EXISTING SFD. (N)AC CENTRAL UNIT.
Permit Issued
Issued on 9/5/2024
Issuing Office
Current Status
Permit Finaled on 5/1/2026

Permit Application Status History

Submitted 11/28/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 MARCELA FRANQUEZ
Corrections Issued 12/2/2023 MARCELA FRANQUEZ
Quality Review Completed 12/14/2023 TU HUA
Applicant returned to address corrections 5/22/2024 MARCELA FRANQUEZ
Applicant returned to address corrections 7/17/2024 MARCELA FRANQUEZ
Plans on Hold 8/22/2024 MARCELA FRANQUEZ
Plan Check Approved 9/5/2024 MARCELA FRANQUEZ
Issued 9/5/2024 APPLICANT
Permit Finaled 4/30/2026 JOHN QUINTANILLA

Permit Application Clearance Information

Low Impact Development (LID) Cleared 4/2/2024 PATRICK LOPEZ
Tenant Habitability Plan Cleared 6/25/2024 ISMAEL HERNANDEZ
ZI Cleared 7/1/2024 MANERI ROMAN
Roof/Waste drainage to street Cleared 8/26/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/27/2024 CHRISTINA BRACO
Sewer availability Cleared 8/27/2024 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Askarian,, Kyle Kambiz; Lic. No.: C86477 136 AGOSTINO      IRVINE, CA 92614

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/14/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 11/25/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 2/4/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 2/4/2025 Not Ready for Inspection JOHN QUINTANILLA
Wood Frame 2/4/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 2/12/2025 No Access for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 2/18/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 2/20/2025 Conditional Approval JOHN QUINTANILLA
Interior/Exterior Lathing 2/20/2025 Approved JOHN QUINTANILLA
MERV13>=Rough 2/20/2025 Approved JOHN QUINTANILLA
Insulation 2/24/2025 Conditional Approval JOHN QUINTANILLA
Insulation 2/28/2025 Approved JOHN QUINTANILLA
Drywall Nailing 3/6/2025 Approved JOHN QUINTANILLA
Shower Pan 3/6/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 3/25/2025 Approved ANTHONY RAMOS
Shower Pan 3/25/2025 Approved ANTHONY RAMOS
Underground Mechanical 4/24/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 9/25/2025 Approved JOHN QUINTANILLA
Final 9/25/2025 Not Ready for Inspection JOHN QUINTANILLA
MERV13>=Final 9/25/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 9/25/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 10/2/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 10/10/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 10/16/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 10/16/2025 Approved JOHN QUINTANILLA
Service/Power Release 10/20/2025 Approved JOHN QUINTANILLA
Final 11/5/2025 Not Ready for Inspection JOHN QUINTANILLA
Smoke Detectors 11/5/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 12/1/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Final 3/9/2026 Corrections Issued JOHN QUINTANILLA
Gas Test 3/13/2026 Approved MICHAEL LEWIS
PLUMBING-Final 3/13/2026 Partial Inspection MICHAEL LEWIS
Final 4/20/2026 Corrections Issued SABAS ALONSO
Smoke Detectors 4/20/2026 Approved SABAS ALONSO
Final 4/30/2026 Permit Finaled JOHN QUINTANILLA