6264 E CHURCH ST 90042

Certificate Information: 6264 E CHURCH ST 90042

Application / Permit
23014-10000-04943
Plan Check / Job No.
B23LA22789
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*eplan* MAJOR REMODEL AND ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE NFPA 13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 1/24/2025
Issuing Office
Current Status
Issued on 1/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/4/2023 APPLICANT
Assigned to Plan Check Engineer 12/21/2023 JAD BASMA
Corrections Issued 12/24/2023 JAD BASMA
Quality Review Completed 1/4/2024 PRANITA SHAH
Applicant returned to address corrections 9/19/2024 JAD BASMA
Applicant returned to address corrections 10/25/2024 JAD BASMA
Applicant returned to address corrections 11/19/2024 JAD BASMA
Plan Check Approved 12/26/2024 JAD BASMA
Issued 1/24/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/1/2024 KURT CORRAL
GPI Written Notices Cleared 10/2/2024 JAD BASMA
Grading Pre-Inspection Cleared 10/2/2024 JAD BASMA
Roof/Waste drainage to street Cleared 10/10/2024 CHRISTINA BRACO
Sewer availability Cleared 10/10/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 10/11/2024 CHRISTINA BRACO
Low Impact Development (LID) Cleared 11/20/2024 ERNEST TSE

Contact Information

Contractor Owner-Builder       ,
Engineer Arutyunyan,, Vladimir; Lic. No.: NA92714       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/13/2025 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 2/13/2025 Not Ready for Inspection CRAIG DAVIS
Pre-Inspection 2/13/2025 Not Ready for Inspection CRAIG DAVIS
Deputy Drilled-In Anchors 3/5/2025 Conditional Approval JOSH MEISTER
Deputy Drilled-In Anchors 3/5/2025 Partial Approval DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 3/5/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 3/5/2025 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 3/10/2025 Approved DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 3/10/2025 Approved DAVID WILLIAMS
Footing/Foundation/Slab 3/10/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 11/13/2025 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Rough 11/13/2025 Approved DAVID WILLIAMS
Green Building Rough 11/13/2025 Approved DAVID WILLIAMS
HVAC-Rough 11/13/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 11/13/2025 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 11/13/2025 Not Ready for Inspection DAVID WILLIAMS
Wood Frame 11/13/2025 Not Ready for Inspection DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Partial Approval DAVID WILLIAMS
BUILDING-Rough-Frame 12/15/2025 Not Ready for Inspection DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 12/15/2025 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 12/15/2025 Not Ready for Inspection DAVID WILLIAMS
Insulation 3/18/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 3/18/2026 Partial Approval DAVID WILLIAMS
Drywall Nailing 3/27/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 3/27/2026 Partial Approval DAVID WILLIAMS
Shower Pan 3/27/2026 Approved DAVID WILLIAMS