2026 W 41ST PL 90062

Certificate Information: 2026 W 41ST PL 90062

Application / Permit
23014-10000-04941
Plan Check / Job No.
B23LA22783
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN (E) GARAGE CONVERSION WITH ADDITION TO ACCESSORY DWELLING UNIT AND PATIO PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/18/2024
Issuing Office
Current Status
CofO Issued on 6/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 MOHAMMAD ESMAILI
Corrections Issued 12/8/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 4/2/2024 MOHAMMAD ESMAILI
Plan Check Approved 4/16/2024 MOHAMMAD ESMAILI
Issued 7/18/2024 APPLICANT
CofO in Progress 6/11/2025 SABAS ALONSO
Permit Finaled 6/12/2025 DEROLD HAUFF
CofO Issued 6/12/2025 DEROLD HAUFF
Permit Finaled 6/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/21/2023 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 2/22/2024 DAVID LOPEZ
Sewer availability Cleared 2/22/2024 DAVID LOPEZ
Low Impact Development (LID) Cleared 3/21/2024 TOMMY YIN
Construction within easement Cleared 3/26/2024 RIDWAN HARDY
Roof/Waste drainage to street Cleared 3/26/2024 DAVID LOPEZ

Contact Information

Contractor Adu Rc Builders; Lic. No.: 1080967-B       ,
Contractor Ca Construction Group Inc; Lic. No.: 1080967-B       ,
Engineer Arutyunyan,, Vladimir; Lic. No.: NA92714       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/7/2024 Partial Approval SABAS ALONSO
Deputy Drilled-In Anchors 8/21/2024 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 8/21/2024 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 8/21/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 No Access for Inspection SABAS ALONSO
HVAC-Rough 10/23/2024 No Access for Inspection SABAS ALONSO
ELECTRICAL-Rough 10/24/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 10/24/2024 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Approved SABAS ALONSO
Green Building Rough 11/4/2024 Corrections Issued SABAS ALONSO
HVAC-Rough 11/4/2024 Approved SABAS ALONSO
PLUMBING-Rough 11/4/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/15/2024 Approved SABAS ALONSO
Green Building Rough 11/15/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 11/15/2024 Partial Approval SABAS ALONSO
Insulation 11/22/2024 Approved SABAS ALONSO
Drywall Nailing 12/3/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 12/3/2024 Approved SABAS ALONSO
Sewer 1/3/2025 Approved BARRY HACHE
Underground Mechanical 1/3/2025 Corrections Issued BARRY HACHE
Interior/Exterior Lathing 1/6/2025 Partial Approval SABAS ALONSO
Underground Mechanical 1/6/2025 Approved SABAS ALONSO
Underground Mechanical 2/26/2025 Approved SABAS ALONSO
Final 5/1/2025 Corrections Issued SABAS ALONSO
Green Building Final 5/1/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/1/2025 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 5/1/2025 Approved SABAS ALONSO
Final 5/9/2025 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Not Ready SABAS ALONSO
Service/Power Release 5/9/2025 Not Ready for Inspection SABAS ALONSO
Final 5/14/2025 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 5/14/2025 Not Ready for Inspection SABAS ALONSO
Service/Power Release 5/16/2025 Not Required SABAS ALONSO
Final 6/11/2025 OK to Issue CofO SABAS ALONSO
Service/Power Release 6/11/2025 Approved SABAS ALONSO