10317 S PALOMA AVE 90002
Certificate Information: 10317 S PALOMA AVE 90002
- Application / Permit
- 23014-10000-04919
- Plan Check / Job No.
- B23LA22741
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT REAR AND FRONT OF EXISTING SFD HOUSE WITH INTERIOR REMODEL/ALTERATION PER PLANS.CONVERT GARAGE TO LAUNDRY ROOM. (NO PARKING PER AB 2097). ALL WORK PER WFPP
- Permit Issued
- Issued on 1/3/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2023 | LUKE GONZALES |
| Corrections Issued | 12/1/2023 | LUKE GONZALES |
| Applicant returned to address corrections | 12/12/2023 | NEHEMIAS RAMOS |
| Plan Check Approved | 12/27/2023 | DANIEL SANJUAN |
| Issued | 1/3/2024 | APPLICANT |
| CofO in Progress | 7/29/2025 | ANTHONY EGSON |
| CofO Issued | 7/29/2025 | ANSON MAGLASANG |
| Permit Finaled | 7/29/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/8/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 12/21/2023 | JUSTIN BICOL |
Contact Information
| Contractor | A & F General Construction Inc; Lic. No.: 1020363-B | 232 WEST 11TH STREET APT 2 SAN PEDRO, CA 90731 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/29/2024 | Conditional Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 4/8/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 7/8/2024 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 7/15/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 7/15/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/22/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 10/22/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/25/2024 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 10/25/2024 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/12/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/12/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/9/2025 | Partial Approval | BEN MOLSTAD |
| Insulation | 2/4/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 2/4/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 2/25/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/20/2025 | Approved | ANTHONY EGSON |
| Final | 4/11/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 4/11/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 4/11/2025 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 4/11/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 5/19/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 5/19/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/19/2025 | Approved | ANTHONY EGSON |
| Green Building Final | 5/19/2025 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 5/19/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 5/19/2025 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 5/19/2025 | Approved | ANTHONY EGSON |
| Final | 6/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 6/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 7/25/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 7/25/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 7/25/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 7/25/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 7/28/2025 | Approved | ANTHONY EGSON |
| Final | 7/28/2025 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 7/28/2025 | Approved | ANTHONY EGSON |