306-308 N ST ANDREWS PL 90004
Certificate Information: 306-308 N ST ANDREWS PL 90004
- Application / Permit
- 23014-10000-04918
- Plan Check / Job No.
- B23LA22738
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New ADUs addition to existing garage. New ADUs on 2nd floor and existing garage to be remained. ADU CHECKED PER CA GOVT. CODE 65852.2(E)(1)(D) AND LAMC 12.22 A.33 (C)-(D),(G)
- Permit Issued
- Issued on 5/30/2024
- Issuing Office
- Current Status
- CofO Issued on 5/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2023 | SUNMIN LEE |
| Corrections Issued | 1/2/2024 | SUNMIN LEE |
| Quality Review Completed | 1/4/2024 | GARO TELMI |
| Applicant returned to address corrections | 3/5/2024 | SUNMIN LEE |
| Plan Check Approved | 4/18/2024 | SUNMIN LEE |
| Issued | 5/30/2024 | APPLICANT |
| CofO in Progress | 5/13/2025 | RAUL BARAJAS |
| Permit Finaled | 5/18/2025 | DEROLD HAUFF |
| CofO Issued | 5/18/2025 | DEROLD HAUFF |
| Permit Finaled | 5/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2024 | WALLIE JONG |
| Construction within easement | Cleared | 2/28/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2024 | WALLIE JONG |
| Sewer availability | Cleared | 3/11/2024 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 4/11/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/16/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hwang,, Junho; Lic. No.: NA5592 | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/6/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 9/9/2024 | Partial Approval | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 9/9/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 9/10/2024 | Corrections Issued | JEFFREY MEAD |
| Deputy Steel/Welding | 9/18/2024 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Reinf. Concrete | 10/2/2024 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Approved | ENRIQUE MIRELES |
| Wood Frame | 10/24/2024 | Corrections Issued | JEFFREY MEAD |
| Gas Test | 11/6/2024 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 11/6/2024 | Approved | BRENDAN MORELLI |
| Sewer | 11/6/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Underground Mechanical | 11/6/2024 | Corrections Issued | BRENDAN MORELLI |
| Insulation | 11/12/2024 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Insulation | 11/15/2024 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 11/27/2024 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 11/27/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 11/27/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 12/4/2024 | Conditional Approval | JEFFREY MEAD |
| Drywall Nailing | 12/11/2024 | Approved | JEFFREY MEAD |
| Green Building Rough | 12/11/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 12/11/2024 | Approved | JEFFREY MEAD |
| Deputy Steel/Welding | 1/9/2025 | Conditional Approval | JEFFREY MEAD |
| PLUMBING-Rough | 1/10/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Final | 2/11/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 2/11/2025 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Final | 2/11/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 2/19/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 2/19/2025 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 2/19/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 2/25/2025 | Approved | JEFFREY MEAD |
| Final | 2/25/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 2/25/2025 | Approved | JEFFREY MEAD |
| Final | 5/8/2025 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 5/8/2025 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/12/2025 | Approved | RAUL BARAJAS |
| Final | 5/12/2025 | OK to Issue CofO | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/12/2025 | Approved | RAUL BARAJAS |