6374 W 82ND ST 90045
Certificate Information: 6374 W 82ND ST 90045
- Application / Permit
- 23014-10000-04865
- Plan Check / Job No.
- B23LA22485
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION AND ADDITION INTO ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part 2 of LAMC 12.22 A.33 (c)-(d), (g) "COMPLY WITH DEPARTMENT ORDER effective date 08/11/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case #991364.
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/5/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 12/11/2023 | APPLICANT |
| Plan Check Approved | 1/5/2024 | GEORGE ALVAREZ |
| Issued | 1/19/2024 | APPLICANT |
| CofO in Progress | 2/27/2025 | ANDREW BEELI |
| Permit Finaled | 3/21/2025 | CLAUDIO MORENO |
| CofO Issued | 3/21/2025 | CLAUDIO MORENO |
| Permit Finaled | 3/21/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2023 | BRENDEN HAWK |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2023 | BRENDEN HAWK |
| Sewer availability | Cleared | 12/12/2023 | BRENDEN HAWK |
| Roof/Waste drainage to street | Cleared | 12/27/2023 | BRENDEN HAWK |
| Specific Plan | Cleared | 12/27/2023 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/31/2024 | Partial Approval | ANDREW BEELI |
| PLUMBING-Rough | 3/22/2024 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 3/28/2024 | Corrections Issued | ANDREW BEELI |
| Excavation/Setback/Form/Re-Bar | 3/29/2024 | Approved | ANDREW BEELI |
| Footing/Foundation/Slab | 4/8/2024 | Partial Inspection | JOHN MATTILLO |
| Underground Mechanical | 4/25/2024 | Approved | ANDREW BEELI |
| Wood Frame | 4/25/2024 | Not Ready for Inspection | ANDREW BEELI |
| Interior/Exterior Lathing | 5/1/2024 | Corrections Issued | ANDREW BEELI |
| Wood Frame | 5/1/2024 | Not Ready for Inspection | ANDREW BEELI |
| BUILDING-Rough-Frame | 5/21/2024 | Corrections Issued | JOHN MATTILLO |
| ELECTRICAL-Rough | 5/21/2024 | Not Ready for Inspection | JOHN MATTILLO |
| Green Building Rough | 5/21/2024 | Not Ready for Inspection | JOHN MATTILLO |
| BUILDING-Rough-Frame | 5/23/2024 | Corrections Issued | JOHN MATTILLO |
| ELECTRICAL-Rough | 5/23/2024 | Not Ready for Inspection | JOHN MATTILLO |
| Green Building Rough | 5/23/2024 | Not Ready for Inspection | JOHN MATTILLO |
| PLUMBING-Rough | 5/23/2024 | Not Ready for Inspection | JOHN MATTILLO |
| BUILDING-Rough-Frame | 5/29/2024 | Partial Approval | JOHN MATTILLO |
| Green Building Rough | 5/29/2024 | Not Ready for Inspection | JOHN MATTILLO |
| ELECTRICAL-Rough | 5/30/2024 | Corrections Issued | JOHN MATTILLO |
| PLUMBING-Rough | 5/30/2024 | Corrections Issued | JOHN MATTILLO |
| ELECTRICAL-Rough | 6/5/2024 | Not Ready for Inspection | JOHN MATTILLO |
| PLUMBING-Rough | 6/5/2024 | Not Ready for Inspection | JOHN MATTILLO |
| ELECTRICAL-Rough | 6/10/2024 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Rough | 6/10/2024 | Corrections Issued | ANDREW BEELI |
| BUILDING-Rough-Frame | 6/11/2024 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Rough | 6/11/2024 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 6/11/2024 | Approved | ANDREW BEELI |
| ELECTRICAL-Rough | 6/20/2024 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 6/20/2024 | Approved | ANDREW BEELI |
| Drywall Nailing | 6/28/2024 | Not Ready for Inspection | JOHN MATTILLO |
| Drywall Nailing | 7/1/2024 | Not Ready for Inspection | JOHN MATTILLO |
| Drywall Nailing | 7/2/2024 | Approved | JOHN MATTILLO |
| BUILDING-Rough-Frame | 9/6/2024 | Partial Approval | ANDREW BEELI |
| Final | 9/6/2024 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 9/6/2024 | Approved | ANDREW BEELI |
| Green Building Final | 9/6/2024 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Rough | 9/6/2024 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 9/6/2024 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 10/17/2024 | Approved | ANDREW BEELI |
| Final | 10/17/2024 | Partial Approval | ANDREW BEELI |
| Green Building Final | 10/17/2024 | Approved | ANDREW BEELI |
| Green Building Rough | 10/17/2024 | Approved | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Approved | ANDREW BEELI |
| Final | 2/27/2025 | OK to Issue CofO | ANDREW BEELI |