1920 W 94TH PL 90047

Certificate Information: 1920 W 94TH PL 90047

Application / Permit
23014-10000-04861
Plan Check / Job No.
B23LA22455
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
17'x27' rear addition to existing 1 story single family dwelling
Permit Issued
Issued on 12/15/2023
Issuing Office
Metro
Current Status
Issued on 12/15/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/28/2023 APPLICANT
Assigned to Plan Check Engineer 11/29/2023 AUNG SOE
Corrections Issued 12/4/2023 AUNG SOE
Building Plans Picked Up 12/8/2023 APPLICANT
Plan Check Approved 12/14/2023 ADAM HEGAZI
Issued 12/15/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/13/2023 JUSTIN BICOL
Sewer availability Cleared 12/13/2023 JUSTIN BICOL
Roof/Waste drainage to street Cleared 12/14/2023 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/3/2024 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 1/4/2024 Approved ENRIQUE MIRELES
METHANE-Barrier 1/4/2024 Approved ENRIQUE MIRELES
METHANE-Subgrade 1/4/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/9/2024 Approved ENRIQUE MIRELES
Green Building Rough 1/9/2024 Approved ENRIQUE MIRELES
METHANE-Rough 1/9/2024 Approved ENRIQUE MIRELES
Insulation 1/10/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 1/26/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/26/2024 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 1/26/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 1/26/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/2/2024 Corrections Issued ENRIQUE MIRELES
Wood Frame 2/2/2024 Approved ENRIQUE MIRELES
Insulation 2/6/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/6/2024 Approved ENRIQUE MIRELES
Drywall Nailing 2/7/2024 Approved ENRIQUE MIRELES
Shower Pan 2/15/2024 Approved JOSE MACIAS
Final 3/19/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 3/19/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 3/19/2024 Corrections Issued MICHAEL LEWIS