12909 W WALSH AVE 90066
Certificate Information: 12909 W WALSH AVE 90066
- Application / Permit
- 23014-10000-04855
- Plan Check / Job No.
- B23LA22432
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL OF EXISTING SINGLE FAMILY DWELLING - PER ENGINEER AUTOMATIC FIRE SPRINKLER SYSTEM REQUIRED.
- Permit Issued
- Issued on 5/30/2024
- Issuing Office
- Current Status
- Issued on 5/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 12/2/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 4/1/2024 | ROSENDO MEDINA |
| Plan Check Approved | 5/29/2024 | ROSENDO MEDINA |
| Issued | 5/30/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/2/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 2/15/2024 | LIAM ODONOVAN |
| Specific Plan | Cleared | 2/20/2024 | PEDRO AYALA |
Contact Information
| Architect | Gelfat,, James Evan; Lic. No.: NA19847 | , |
| Contractor | Guideline Builders Inc; Lic. No.: 1021305-B | , |
| Engineer | Parker,, Leo Augustine; Lic. No.: NA2829 | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/12/2024 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 6/17/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 6/24/2024 | Approved | TEMISTOCLES CAAL |
| Deputy Wood Construction | 7/16/2024 | Conditional Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 7/19/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2024 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 7/19/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 8/5/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/5/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 8/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Rough | 8/12/2024 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 8/12/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 8/14/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 8/14/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 8/19/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 8/23/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 10/7/2024 | Corrections Issued | HERBERT GIRON |
| Final | 10/7/2024 | Corrections Issued | HERBERT GIRON |
| Gas Test | 10/7/2024 | Approved | HERBERT GIRON |
| Green Building Final | 10/7/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 10/7/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 10/7/2024 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 10/7/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 10/8/2024 | Approved | TEMISTOCLES CAAL |
| Gas Test | 10/8/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 10/8/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 10/8/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 11/13/2024 | Approved | BOBBY KEY |