9606-9606 1/2 S GRAPE ST 90002
Certificate Information: 9606-9606 1/2 S GRAPE ST 90002
- Application / Permit
- 23014-10000-04850
- Plan Check / Job No.
- B23LA22407
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* 2ND STORY ATTACHED ADU ADDITION TO (E) 1-STORY SFD WITH ATTACHED 2-CAR GARAGE PER LAMC 12.22A.33(c) AND (e). NFPA 13D COMPLY WITH DEPARTMENT ORDER effective date 06/28/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 6/28/2024
- Issuing Office
- Current Status
- CofO Issued on 9/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | VIVIAN LAO |
| Corrections Issued | 12/2/2023 | VIVIAN LAO |
| Quality Review Completed | 12/7/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 5/8/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 6/5/2024 | VIVIAN LAO |
| Plan Check Approved | 6/18/2024 | VIVIAN LAO |
| Issued | 6/28/2024 | APPLICANT |
| CofO in Progress | 8/29/2025 | ANTHONY EGSON |
| Permit Finaled | 9/11/2025 | ANSON MAGLASANG |
| CofO Issued | 9/11/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/18/2023 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 12/18/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 1/23/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Zetino And Son'S Construction; Lic. No.: 817787-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/17/2024 | Conditional Approval | BEN MOLSTAD |
| Deputy Other (see comments) | 7/17/2024 | Conditional Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 7/17/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 7/24/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 7/30/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 8/20/2024 | Partial Approval | BEN MOLSTAD |
| Gas Test | 8/20/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 8/20/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Not Ready for Inspection | BARRY HACHE |
| Insulation | 8/26/2024 | Corrections Issued | BARRY HACHE |
| Special/Order Compliance | 8/26/2024 | Partial Approval | BEN MOLSTAD |
| Insulation | 8/29/2024 | Partial Approval | BEN MOLSTAD |
| Special/Order Compliance | 8/29/2024 | Partial Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Corrections Issued | BARRY HACHE |
| Special/Order Compliance | 9/3/2024 | Partial Inspection | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Approved | BARRY HACHE |
| Sewer | 9/18/2024 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 10/2/2024 | Partial Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/2/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/2/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/2/2024 | Approved | JOSEPH MCGARRY |
| Sewer | 10/2/2024 | Approved | JOSEPH MCGARRY |
| Shower Pan | 10/2/2024 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/23/2024 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 10/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/19/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 11/19/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 11/25/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 11/25/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/2/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 12/2/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 12/5/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/10/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/19/2024 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/19/2024 | Partial Approval | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 12/19/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 12/24/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/13/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/30/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 4/30/2025 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 4/30/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 4/30/2025 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 4/30/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 4/30/2025 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 4/30/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 4/30/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 5/21/2025 | Approved | ANTHONY EGSON |
| Gas Test | 5/21/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 5/21/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 5/21/2025 | Approved | ANTHONY EGSON |
| Service/Power Release | 5/21/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | ANTHONY EGSON |
| Final | 8/29/2025 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 8/29/2025 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 8/29/2025 | Approved | ANTHONY EGSON |