4559 N PETIT AVE 91436
Certificate Information: 4559 N PETIT AVE 91436
- Application / Permit
- 23014-10000-04845
- Plan Check / Job No.
- B23LA22359
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO EXISTING SINGLE-FAMILY DWELLING WITH 11'-10" X 17'-5 1/2" ADDITION AT ENTRANCE OF SFD. CONVERT BREEZEWAY TO CONDITIONED AREA (DINING ROOM). REMOVE AND REPLACE WINDOWS/DOORS PER PLAN. ALL WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 2/12/2024
- Issuing Office
- Current Status
- Issued on 2/12/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 12/1/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 1/12/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 1/30/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 2/5/2024 | OMAR GARNICA |
| Plan Check Approved | 2/11/2024 | OMAR GARNICA |
| Issued | 2/12/2024 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/1/2023 | ALEC MOUSAKHANIAN |
| Roof/Waste drainage to street | Cleared | 1/26/2024 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samara,, Muzahim; Lic. No.: C26015 | 9100 S SEPULVEDA BLVD SUITE 115 LOS ANGELES, CA 90045 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 3/1/2024 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/2/2024 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/8/2024 | Approved | VINCENT HANLEY |
| Deputy Steel/Welding | 5/2/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 5/3/2024 | Conditional Approval | HENRY KIM |
| BUILDING-Rough-Frame | 5/7/2024 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 5/7/2024 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/21/2024 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 5/21/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Partial Approval | SEAN WIRCH |
| ELECTRICAL-Rough | 6/13/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/13/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/17/2024 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/17/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/17/2024 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 7/22/2024 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/11/2024 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 9/11/2024 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/18/2024 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/18/2024 | Approved | THOMAS FINNILA |
| Green Building Rough | 9/18/2024 | Approved | THOMAS FINNILA |
| Insulation | 9/26/2024 | Partial Approval | ALEXANDER HANDY |
| Drywall Nailing | 10/8/2024 | Partial Approval | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 10/16/2024 | Corrections Issued | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 10/22/2024 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/3/2025 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 2/3/2025 | Approved | JOHN COLEMAN |
| HVAC-Rough | 2/3/2025 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 2/10/2025 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/10/2025 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 2/10/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/20/2025 | No Access for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/24/2025 | Corrections Issued | THOMAS FINNILA |
| Insulation | 2/28/2025 | Partial Inspection | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Corrections Issued | JOHN COLEMAN |
| BUILDING-Rough-Frame | 3/6/2025 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Partial Approval | KRISTEN CAUSEY |
| Shower Pan | 4/7/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 4/21/2025 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 5/12/2025 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/13/2025 | Partial Approval | JUAN ALVARADO |