4050 N HARCLARE LANE 91436

Certificate Information: 4050 N HARCLARE LANE 91436

Application / Permit
23014-10000-04830
Plan Check / Job No.
B23LA22279
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Proposed one story front addition of new Entry, new Pantry, and new Covered front porch.
Permit Issued
Issued on 4/9/2024
Issuing Office
Current Status
CofO Issued on 7/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2023 APPLICANT
Assigned to Plan Check Engineer 11/28/2023 JOSEPH RAFOLS
Corrections Issued 11/28/2023 JOSEPH RAFOLS
Plan Check Approved 12/10/2023 SAMUEL GONZALEZ
Issued 4/9/2024 APPLICANT
CofO in Progress 2/14/2025 THOMAS FINNILA
No Progress 6/16/2025 SEAN WIRCH
CofO in Progress 6/16/2025 SEAN WIRCH
Permit Finaled 7/21/2025 DANIEL ORRANTE
CofO Issued 7/21/2025 DANIEL ORRANTE
Permit Finaled 7/21/2025 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/2/2023 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/2/2023 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/2/2023 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/2/2023 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/2/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/2/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/6/2023 LEE GUILBEAUX
Grading Pre-Inspection Cleared 12/7/2023 MICHAEL TEMPLE

Contact Information

Architect Woodcraft,, Lawrence Albert; Lic. No.: C23651 20812 VENTURA BLVD, STE 205      WOODLAND HILLS, CA 91364
Architect Woodcraft,, Lawrence Albert; Lic. No.: NA23651       ,
Contractor Omni General Construction; Lic. No.: 500639-B       ,
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364
Engineer Tan,, Henreik Steven; Lic. No.: NA65723       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/18/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/18/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/25/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 6/26/2024 Not Ready for Inspection THOMAS FINNILA
Wood Frame 7/2/2024 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 7/24/2024 Approved THOMAS FINNILA
ELECTRICAL-Rough 7/24/2024 Approved THOMAS FINNILA
PLUMBING-Rough 7/24/2024 Approved THOMAS FINNILA
Insulation 7/26/2024 Approved THOMAS FINNILA
Drywall Nailing 8/1/2024 Approved ALEXANDER HANDY
Gas Test 10/3/2024 Approved MORRIS JACKSON
ELECTRICAL-Final 11/21/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Final 11/21/2024 Approved THOMAS FINNILA
Final 12/2/2024 Conditional Approval THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Approved THOMAS FINNILA
Smoke Detectors 12/2/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 2/13/2025 Approved THOMAS FINNILA
Final 2/13/2025 OK to Issue CofO THOMAS FINNILA