3158 1/4 S HELMS AVE 90034
Certificate Information: 3158 1/4 S HELMS AVE 90034
- Application / Permit
- 23014-10000-04809
- Plan Check / Job No.
- B23LA22214
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT EXISTING DETACHED GARAGE TO ADU AND ADDITION PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/17/2024
- Issuing Office
- Current Status
- CofO Issued on 8/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2023 | NEHEMIAS RAMOS |
| Corrections Issued | 11/30/2023 | NEHEMIAS RAMOS |
| Plan Check Approved | 4/17/2024 | RICARDO RAMIREZ |
| Issued | 4/17/2024 | APPLICANT |
| CofO in Progress | 8/16/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 8/17/2024 | RICHARD STEINBACH |
| CofO Issued | 8/17/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/17/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 1/9/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2024 | WALLIE JONG |
| Sewer availability | Cleared | 1/10/2024 | WALLIE JONG |
| Construction near power lines | Cleared | 4/8/2024 | RIDWAN HARDY |
| ZI | Cleared | 4/10/2024 | ISAIAH ROSS |
| ZI | Cleared | 4/11/2024 | JULISSA LOPEZ-HODOYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/19/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 4/24/2024 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 4/24/2024 | Approved | SEAN HAUPT |
| Insulation | 5/10/2024 | Partial Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 5/10/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/16/2024 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 5/16/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/16/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 5/20/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/20/2024 | Partial Approval | MEL KHACHATOURIAN |
| Sewer | 5/22/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 5/22/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/28/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 5/28/2024 | Approved | MEL KHACHATOURIAN |
| MERV13>=Rough | 5/28/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 5/30/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/30/2024 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 6/5/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 6/5/2024 | Approved | MEL KHACHATOURIAN |
| Final | 8/1/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 8/1/2024 | Approved | MEL KHACHATOURIAN |
| MERV13>=Final | 8/1/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 8/1/2024 | Approved | MEL KHACHATOURIAN |
| Final | 8/14/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2024 | SGSOV Approved | MEL KHACHATOURIAN |