8100 S WINSFORD AVE 90045
Certificate Information: 8100 S WINSFORD AVE 90045
- Application / Permit
- 23014-10000-04805
- Plan Check / Job No.
- B23LA22208
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 44'-0" x 37-9" IRREGULAR SHAPED ADDITION TO THE (E) SINGLE FAMILY DWELLING WITH (N) 11'-11" x 19'-2" ATTACHED CARPORT ADDITION. NFPA 13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/8/2024
- Issuing Office
- Current Status
- CofO Issued on 4/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2023 | ISIS ARGUETA |
| Corrections Issued | 11/30/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 2/22/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 2/27/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 3/2/2024 | GIOVANNY CHAVEZ |
| Issued | 3/8/2024 | APPLICANT |
| CofO in Progress | 4/2/2025 | JESUS PINEDA |
| Permit Finaled | 4/9/2025 | RICHARD STEINBACH |
| CofO Issued | 4/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/15/2023 | EDUARDO HERMOSO |
| Grading Pre-Inspection | Cleared | 12/19/2023 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2023 | ERIK BEASLEY |
| Sewer availability | Cleared | 12/20/2023 | ERIK BEASLEY |
| Low Impact Development (LID) | Cleared | 2/15/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 2/15/2024 | JEANIE LAM |
Contact Information
| Contractor | Masumori Yuji; Lic. No.: 965154-B | 116 MARMION WAY #7 SOUTH PASADENA, CA 91030 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 4/23/2024 | Approved | BOBBY KEY |
| Wood Frame | 4/23/2024 | Partial Approval | BOBBY KEY |
| Insulation | 4/25/2024 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/25/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/26/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Partial Approval | BOBBY KEY |
| Insulation | 4/30/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 4/30/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 6/10/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 6/21/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 6/21/2024 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 6/28/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 6/28/2024 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 7/2/2024 | Partial Approval | BOBBY KEY |
| Gas Test | 7/2/2024 | Approved | BOBBY KEY |
| Green Building Rough | 7/2/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 7/2/2024 | Approved | BOBBY KEY |
| Insulation | 7/2/2024 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 7/2/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 7/2/2024 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 7/2/2024 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 7/9/2024 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 7/9/2024 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 7/12/2024 | Approved | BOBBY KEY |
| Green Building Rough | 7/12/2024 | Approved | BOBBY KEY |
| Insulation | 7/12/2024 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 7/12/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 7/17/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 7/19/2024 | Partial Approval | BOBBY KEY |
| Shower Pan | 7/19/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 7/30/2024 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 8/2/2024 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 8/9/2024 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 9/17/2024 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 9/17/2024 | Approved | TEMISTOCLES CAAL |
| Final | 9/19/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 9/19/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 9/19/2024 | Approved | BOBBY KEY |
| Gas Test | 9/24/2024 | Approved | BOBBY KEY |
| Final | 9/27/2024 | Partial Inspection | MICHAEL ALLEN |
| Green Building Final | 9/27/2024 | Corrections Issued | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Approved | MICHAEL ALLEN |
| Final | 4/2/2025 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 4/2/2025 | Approved | JESUS PINEDA |