15485-15487 W HAMNER DR 90077
Certificate Information: 15485-15487 W HAMNER DR 90077
- Application / Permit
- 23014-10000-04780
- Plan Check / Job No.
- B23LA22073
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE AND PORTION OF (E) SFD TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ADD ROOF COVER WITH SKYLIGHTS TO (E) OPEN COURTYARD. REMOVE AND REPLACE DAMAGED ROOF AND INSTALL NEW ROOF WATERPROOFING. ALL WORK PER ENGINEERED DESIGN. BUILDING TO BE EQUIPPED WITH NFPA 13D FIRE SPRINKLERS THORUGHOUT. "COMPLY WITH DEPARTMENT ORDER effective date 09/09/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 4/16/2024
- Issuing Office
- Current Status
- CofO Issued on 5/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2023 | OMAR GARNICA |
| Corrections Issued | 12/8/2023 | OMAR GARNICA |
| Applicant returned to address corrections | 2/9/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/22/2024 | ALEC MOUSAKHANIAN |
| Issued | 4/16/2024 | APPLICANT |
| CofO in Progress | 3/12/2026 | RUBEN PEREZ |
| Permit Finaled | 5/8/2026 | DANIEL SANCHEZ |
| CofO Issued | 5/8/2026 | DANIEL SANCHEZ |
| Permit Finaled | 5/8/2026 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 12/26/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 12/26/2023 | DARIN LAM |
| Sewer availability | Cleared | 12/26/2023 | DARIN LAM |
| ZA Case | Cleared | 12/26/2023 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2023 | DARIN LAM |
| Specific Plan | Cleared | 3/20/2024 | KATIE DEBIASE |
Contact Information
| Architect | Getov,, Pavel Panayotov; Lic. No.: C32093 | 3565 REDWOOD AVENUE LOS ANGELES, CA 90066 |
| Contractor | Everest Construct Inc; Lic. No.: 1075122-B | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/12/2024 | Approved | RUBEN PEREZ |
| Excavation/Setback/Form/Re-Bar | 6/28/2024 | Approved | RUBEN PEREZ |
| Footing/Foundation/Slab | 6/28/2024 | Approved | RUBEN PEREZ |
| Excavation/Setback/Form/Re-Bar | 7/17/2024 | Approved | RUBEN PEREZ |
| Deputy Wood Construction | 8/9/2024 | Conditional Approval | PETER RUBIO |
| BUILDING-Rough-Frame | 8/13/2024 | Not Ready for Inspection | PETER RUBIO |
| ELECTRICAL-Rough | 8/13/2024 | Not Ready for Inspection | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Partial Approval | PETER RUBIO |
| Green Building Rough | 8/13/2024 | Approved | PETER RUBIO |
| HVAC-Rough | 8/13/2024 | Not Ready for Inspection | PETER RUBIO |
| PLUMBING-Rough | 8/13/2024 | Approved | PETER RUBIO |
| Verify Sprinkler Sign Off | 8/13/2024 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 8/20/2024 | Approved | PETER RUBIO |
| ELECTRICAL-Rough | 8/20/2024 | Approved | PETER RUBIO |
| HVAC-Rough | 8/20/2024 | Approved | PETER RUBIO |
| Drywall Nailing | 8/26/2024 | Approved | PETER RUBIO |
| Insulation | 8/26/2024 | Approved | PETER RUBIO |
| Interior/Exterior Lathing | 8/29/2024 | Approved | PETER RUBIO |
| Final | 12/12/2024 | Not Ready for Inspection | PETER RUBIO |
| Green Building Final | 12/12/2024 | Not Ready for Inspection | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Not Required | PETER RUBIO |
| Smoke Detectors | 12/12/2024 | Not Ready for Inspection | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Corrections Issued | ROBERT CHAVEZ |
| Interior/Exterior Lathing | 2/7/2025 | Approved | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Approved | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Approved | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | Approved | PETER RUBIO |
| ELECTRICAL-Final | 3/6/2026 | Approved | PETER RUBIO |
| Final | 3/6/2026 | Conditional Approval | PETER RUBIO |
| Green Building Final | 3/6/2026 | Approved | PETER RUBIO |
| HVAC-Final | 3/6/2026 | Approved | PETER RUBIO |
| PLUMBING-Final | 3/6/2026 | Approved | PETER RUBIO |
| Smoke Detectors | 3/6/2026 | Approved | PETER RUBIO |
| Final | 3/12/2026 | OK to Issue CofO | RUBEN PEREZ |