131 1/2 E 74TH ST 90003
Certificate Information: 131 1/2 E 74TH ST 90003
- Application / Permit
- 23014-10000-04770
- Plan Check / Job No.
- B23LA22030
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AN (E) DETACHED ADU PERMITTED UNDER 18010-70000-05395 PER ORDINANCE AND LAMC 12.22 A33 (c)&(d).ALL WORK PER ENGINEER DESIGN. ONLY ONE ADU PERMITTED ON THE LOT.
- Permit Issued
- Issued on 4/1/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2023 | ZAW HAN |
| Corrections Issued | 11/27/2023 | ZAW HAN |
| Building Plans Picked Up | 11/28/2023 | APPLICANT |
| Plan Check Approved | 4/1/2024 | JOSE VELAZQUEZ |
| Issued | 4/1/2024 | APPLICANT |
| CofO in Progress | 8/26/2024 | MICHAEL LEWIS |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 1/30/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 1/30/2024 | DAVID VO |
| Tenant Habitability Plan | Cleared | 3/18/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/2/2024 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/13/2024 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Partial Approval | MICHAEL LEWIS |
| Insulation | 5/17/2024 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/6/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/6/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/18/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/18/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 6/18/2024 | Partial Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 6/18/2024 | Approved | MICHAEL LEWIS |
| Insulation | 6/25/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 6/27/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 7/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/29/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/13/2024 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/13/2024 | Approved | MICHAEL LEWIS |
| Green Building Final | 8/13/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Approved | MICHAEL LEWIS |
| Final | 8/23/2024 | OK to Issue CofO | MICHAEL LEWIS |