1107 N SOMERA ROAD 90077

Certificate Information: 1107 N SOMERA ROAD 90077

Application / Permit
23014-10000-04763
Plan Check / Job No.
B23LA21983
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND FLOOR ADDITION AND REMODEL TO (E) 2 STORY SFD W/ATTACHED GARAGE BUILDING BE TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS
Permit Issued
Issued on 4/12/2024
Issuing Office
Current Status
Issued on 4/12/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/20/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 CRYSTEL MAALOUF
Corrections Issued 12/11/2023 CRYSTEL MAALOUF
Quality Review Completed 12/21/2023 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 1/25/2024 CRYSTEL MAALOUF
Applicant returned to address corrections 2/2/2024 CRYSTEL MAALOUF
Plan Check Approved 2/20/2024 CRYSTEL MAALOUF
Issued 4/12/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/13/2023 LIAM ODONOVAN
BHO/Hillside ordinance Cleared 12/13/2023 LIAM ODONOVAN
BHO/Hillside ordinance Cleared 12/13/2023 LIAM ODONOVAN
BHO/Hillside ordinance Cleared 12/13/2023 LIAM ODONOVAN
BHO/Hillside ordinance Cleared 12/13/2023 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 12/15/2023 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 12/15/2023 LIAM ODONOVAN
Sewer availability Cleared 12/15/2023 LIAM ODONOVAN
Grading Pre-Inspection Cleared 1/24/2024 VASIL MIHALEV
Hydrant and Access approval Cleared 2/6/2024 LAVEON RIDER
GPI Written Notices Cleared 2/20/2024 ROBERT PINA

Contact Information

Contractor Y A G Construction; Lic. No.: 769970-B       ,
Engineer Mah,, Edwin Poy-Dor; Lic. No.: C27141 1740 APPIAN WAY      MONTEBELLO, CA 90640

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/12/2025 Approved BOBBY KEY
Masonry Wall/Backfill 2/26/2025 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/28/2025 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 8/19/2025 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 8/21/2025 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Conditional Approval CHRISTOPHER WILSON
Special/Order Compliance 9/8/2025 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/8/2025 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/17/2025 Partial Approval CARLOS MATAMOROS
Verify Sprinkler Sign Off 11/17/2025 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 12/9/2025 Partial Approval CHRISTOPHER WILSON
Gas Test 12/9/2025 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 12/9/2025 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 12/11/2025 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 12/11/2025 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 12/12/2025 Approved CHRISTOPHER WILSON
HVAC-Rough 12/16/2025 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 12/24/2025 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/20/2026 Approved CHRISTOPHER WILSON
Green Building Rough 1/20/2026 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 1/20/2026 Approved CHRISTOPHER WILSON
Insulation 1/21/2026 Approved CHRISTOPHER WILSON
Drywall Nailing 2/9/2026 Approved CARLOS MATAMOROS
Shower Pan 2/23/2026 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 3/11/2026 Partial Approval CHRISTOPHER WILSON
Sewer 3/11/2026 Approved CHRISTOPHER WILSON
Shower Pan 3/11/2026 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 5/13/2026 Approved RYAN SALAZAR