5634 N COLUMBUS AVE 91411
Certificate Information: 5634 N COLUMBUS AVE 91411
- Application / Permit
- 23014-10000-04742
- Plan Check / Job No.
- B23LA21906
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: (N) ADDITION TO SFD AND RE-FRAME ROOF THROUGHOUT
- Permit Issued
- Issued on 4/4/2024
- Issuing Office
- Current Status
- Issued on 4/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/23/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/29/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/2/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/4/2024 | ISIS ARGUETA |
| Issued | 4/4/2024 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 3/20/2024 | ROGELIO CORTES |
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/28/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/29/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Builders Hub Renovation Inc; Lic. No.: 1063741-B | , |
| Engineer | Boules,, George H; Lic. No.: NA64144 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/29/2024 | Conditional Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 5/31/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Partial Approval | RYAN SALAZAR |
| Insulation | 7/22/2024 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 8/21/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/27/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/27/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Wood Frame | 9/27/2024 | Partial Approval | RYAN SALAZAR |
| Insulation | 10/9/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/9/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 10/22/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/22/2024 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 10/31/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/31/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/30/2025 | Approved | RYAN SALAZAR |
| Final | 10/30/2025 | Corrections Issued | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/30/2025 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 10/30/2025 | Approved | RYAN SALAZAR |
| Smoke Detectors | 10/30/2025 | Approved | RYAN SALAZAR |