1020 W 77TH ST 90044

Certificate Information: 1020 W 77TH ST 90044

Application / Permit
23014-10000-04737
Plan Check / Job No.
B23LA21895
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of 569 SF to existing 1-story single family dwelling. All work per engineer.
Permit Issued
Issued on 3/17/2024
Issuing Office
Current Status
CofO Issued on 1/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 VICTOR CHEN
Corrections Issued 11/21/2023 VICTOR CHEN
Applicant returned to address corrections 2/15/2024 SHANGQIN XIE
Applicant returned to address corrections 2/21/2024 DANIEL SMILEY
Plan Check Approved 2/22/2024 ALEC MOUSAKHANIAN
Issued 3/17/2024 APPLICANT
CofO in Progress 1/14/2026 BARRY HACHE
Permit Finaled 1/16/2026 DEROLD HAUFF
CofO Issued 1/16/2026 DEROLD HAUFF
Permit Finaled 1/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/30/2023 JUSTIN BICOL
Sewer availability Cleared 11/30/2023 JUSTIN BICOL
Low Impact Development (LID) Cleared 2/13/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 2/14/2024 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/16/2024 Not Ready for Inspection MICHAEL LEWIS
Pre-Inspection 4/16/2024 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 4/24/2024 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 4/29/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 5/9/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 5/29/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 6/11/2024 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 6/13/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Partial Approval MICHAEL LEWIS
Insulation 6/25/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Partial Approval MICHAEL LEWIS
Green Building Rough 7/31/2024 Not Ready for Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 8/15/2024 Corrections Issued MICHAEL LEWIS
Green Building Rough 8/15/2024 Approved MICHAEL LEWIS
Rough-Elec/Plmb/HVAC 8/15/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 8/20/2024 Partial Approval MICHAEL LEWIS
Interior/Exterior Lathing 8/20/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 8/29/2024 Approved MICHAEL LEWIS
Shower Pan 8/29/2024 Approved MICHAEL LEWIS
Insulation 9/24/2024 Partial Approval ANTHONY RAMOS
BUILDING-Rough-Frame 10/1/2024 Approved SABAS ALONSO
Drywall Nailing 10/1/2024 Approved SABAS ALONSO
Insulation 10/1/2024 Approved SABAS ALONSO
Final 11/13/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 11/13/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 11/13/2024 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 11/13/2024 Approved MICHAEL LEWIS
Final 2/7/2025 Partial Approval JOHN QUINTANILLA
Final 6/24/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 10/27/2025 Approved JOHN QUINTANILLA
HVAC-Final 10/27/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 10/27/2025 Approved JOHN QUINTANILLA
Final 10/30/2025 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Final 11/17/2025 Partial Inspection JOHN QUINTANILLA
Final 1/14/2026 OK to Issue CofO BARRY HACHE