6410 W INNSDALE DR 90068
Certificate Information: 6410 W INNSDALE DR 90068
- Application / Permit
- 23014-10000-04729
- Plan Check / Job No.
- B23LA21863
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: 1ST AND 2ND STORY ADDITION TO (E) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 8/24/2024
- Issuing Office
- Current Status
- CofO Issued on 6/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | DANIEL YIP |
| Corrections Issued | 12/2/2023 | DANIEL YIP |
| Quality Review Completed | 12/6/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/29/2024 | DANIEL YIP |
| Applicant returned to address corrections | 8/14/2024 | DANIEL YIP |
| Plan Check Approved | 8/23/2024 | DANIEL YIP |
| Issued | 8/24/2024 | APPLICANT |
| CofO in Progress | 5/27/2025 | BRIAN SULLIVAN |
| Permit Finaled | 6/8/2025 | DEROLD HAUFF |
| CofO Issued | 6/8/2025 | DEROLD HAUFF |
| Permit Finaled | 6/8/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/21/2023 | RUSSELL BONVOULOIR |
| Construction near power lines | Cleared | 4/8/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 4/22/2024 | WALLIE JONG |
Contact Information
| Architect | Marshall,, Ronald H; Lic. No.: C7598 | 2363 MORSLAY ROAD ALTADENA, CA 91001 |
| Contractor | Owner-Builder | , |
| Engineer | Ferguson,, Pamela Beth; Lic. No.: NA56545 | , |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/8/2024 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/9/2024 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/11/2024 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 10/29/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 11/8/2024 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 11/8/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 11/25/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 3/7/2025 | Approved | BRENDAN MORELLI |
| Insulation | 3/7/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 3/7/2025 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 3/26/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| Gas Test | 3/26/2025 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/26/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/9/2025 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/15/2025 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/15/2025 | Approved | BRIAN SULLIVAN |
| Insulation | 4/28/2025 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 5/7/2025 | Approved | BRIAN SULLIVAN |
| Final | 5/23/2025 | OK to Issue CofO | BRIAN SULLIVAN |
| Green Building Final | 5/23/2025 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 5/23/2025 | Approved | BRIAN SULLIVAN |