919 E INDIANA AVE 90291

Certificate Information: 919 E INDIANA AVE 90291

Application / Permit
23014-10000-04720
Plan Check / Job No.
B23LA21807
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to rear of (e) single family dwelling. All construction per Architect of Record.
Permit Issued
Issued on 12/6/2023
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 LUKE GONZALES
Corrections Issued 11/16/2023 LUKE GONZALES
Applicant returned to address corrections 11/28/2023 LUKE GONZALES
Plan Check Approved 12/6/2023 CRISTINA SALAZAR
Issued 12/6/2023 APPLICANT
CofO in Progress 4/9/2024 HERBERT GIRON
Permit Finaled 4/16/2024 DANIEL ORRANTE
CofO Issued 4/16/2024 DANIEL ORRANTE
Permit Finaled 4/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/21/2023 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 11/21/2023 HISASHI KOBAYAKAWA

Contact Information

Architect Thibodeau,, Robert E; Lic. No.: C25585 812 LINCOLN BLVD      VENICE, CA 90291
Contractor Owner-Builder       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/13/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 12/19/2023 Partial Approval HERBERT GIRON
Insulation 12/19/2023 Partial Approval HERBERT GIRON
PLUMBING-Rough 12/19/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 1/17/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 1/17/2024 Approved HERBERT GIRON
Green Building Rough 1/17/2024 Approved HERBERT GIRON
HVAC-Rough 1/17/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 1/17/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 1/17/2024 Approved HERBERT GIRON
Insulation 1/19/2024 Approved TEMISTOCLES CAAL
Shower Pan 1/19/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 1/22/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 1/22/2024 Not Ready for Inspection TEMISTOCLES CAAL
Interior/Exterior Lathing 1/26/2024 Approved HERBERT GIRON
ELECTRICAL-Final 3/21/2024 Approved HERBERT GIRON
Final 3/21/2024 Corrections Issued HERBERT GIRON
Green Building Final 3/21/2024 Approved HERBERT GIRON
HVAC-Final 3/21/2024 Approved HERBERT GIRON
PLUMBING-Final 3/21/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/21/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 3/21/2024 Corrections Issued HERBERT GIRON
Final 4/2/2024 Corrections Issued HERBERT GIRON
Smoke Detectors 4/2/2024 Approved HERBERT GIRON
Final 4/8/2024 OK to Issue CofO HERBERT GIRON