4411 N NOELINE AVE 91436
Certificate Information: 4411 N NOELINE AVE 91436
- Application / Permit
- 23014-10000-04718
- Plan Check / Job No.
- B23LA21790
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION AND REMODEL TO (E) SFD ADD NEW BASEMENT (1 LEVEL) TO (E) SFD
- Permit Issued
- Issued on 9/17/2024
- Issuing Office
- Current Status
- Issued on 9/17/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2023 | CARLOS MONTES |
| Corrections Issued | 12/24/2023 | CARLOS MONTES |
| Quality Review Completed | 12/28/2023 | GARO TELMI |
| Applicant returned to address corrections | 3/5/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 4/10/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 6/5/2024 | CARLOS MONTES |
| Plan Check Approved | 8/21/2024 | CARLOS MONTES |
| Issued | 9/17/2024 | APPLICANT |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 1/30/2024 | DAVID URITA |
| Tract Map conditions | Cleared | 1/30/2024 | DAVID URITA |
| Tract Map conditions | Cleared | 1/30/2024 | DAVID URITA |
| Tract Map conditions | Cleared | 1/30/2024 | DAVID URITA |
| Tract Map conditions | Cleared | 1/30/2024 | DAVID URITA |
| Tract Map conditions | Cleared | 1/30/2024 | DAVID URITA |
| BHO/Hillside ordinance | Cleared | 2/9/2024 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 2/9/2024 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 2/9/2024 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 2/9/2024 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 2/9/2024 | EDGAR ALCARAZ |
| Distance to fire station | Cleared | 2/12/2024 | MATTHEW CRAIG |
| Hydrant and Access approval | Cleared | 2/12/2024 | MATTHEW CRAIG |
| Sewer availability | Cleared | 2/14/2024 | EDGAR ALCARAZ |
| GPI Written Notices | Cleared | 3/5/2024 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 3/5/2024 | CARLOS MONTES |
| Address approval | Cleared | 4/10/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2024 | CARLOS RAMIREZ |
| Low Impact Development (LID) | Cleared | 5/2/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/3/2024 | EDGAR ALCARAZ |
Contact Information
| Architect | Tolkin,, Peter Loren; Lic. No.: NA30167 | , |
| Contractor | Arrowhead Remodeling & Design Inc; Lic. No.: 935108-B | , |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
| Engineer | Perazzelli,, Joseph Ames; Lic. No.: C35270 | 183 GREENFIELD AVENUE LOS ANGELES, CA 90049 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| PLUMBING-Final | 6/8/2026 |
| HVAC-Final | 6/8/2026 |
Inspection Request History
| Pre-Inspection | 10/3/2024 | Partial Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 11/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 11/1/2024 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/12/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 11/12/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 11/12/2024 | Partial Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 11/25/2024 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/26/2024 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 12/26/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 12/27/2024 | Conditional Approval | HENRY KIM |
| Deputy Reinf. Concrete | 12/27/2024 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 12/30/2024 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 1/13/2025 | Not Ready for Inspection | JOHN COLEMAN |
| Reinforced Concrete Frame | 1/13/2025 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 1/16/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 1/21/2025 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/21/2025 | Corrections Issued | JOHN COLEMAN |
| Reinforced Concrete Frame | 2/21/2025 | Partial Approval | JOHN COLEMAN |
| Deputy Reinf. Concrete | 2/26/2025 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/6/2025 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 3/6/2025 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 3/11/2025 | Partial Approval | KRISTEN CAUSEY |
| Insulation | 3/25/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/25/2025 | Partial Approval | MORRIS JACKSON |
| Shower Pan | 3/25/2025 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 3/28/2025 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 3/28/2025 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 4/2/2025 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Partial Approval | JOHN COLEMAN |
| Insulation | 4/7/2025 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 4/7/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | No Access for Inspection | JOHN COLEMAN |
| Reinforced Concrete Frame | 4/14/2025 | No Access for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 4/16/2025 | Partial Approval | JOHN COLEMAN |
| Deputy Reinf. Concrete | 4/18/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 5/27/2025 | Conditional Approval | JOHN COLEMAN |
| Green Building Rough | 5/27/2025 | Not Ready for Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 5/29/2025 | Corrections Issued | JOHN COLEMAN |
| Grading Pre-Inspection | 5/29/2025 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 6/16/2025 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/10/2025 | Approved | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 9/10/2025 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 9/19/2025 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 9/19/2025 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/28/2025 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/31/2025 | Approved | THOMAS FINNILA |
| Green Building Rough | 10/31/2025 | Approved | THOMAS FINNILA |
| HVAC-Rough | 10/31/2025 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/31/2025 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 11/13/2025 | Partial Approval | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Partial Approval | JUAN ALVARADO |
| Insulation | 11/13/2025 | Approved | JUAN ALVARADO |