7140 W HOCKEY TR 90068

Certificate Information: 7140 W HOCKEY TR 90068

Application / Permit
23014-10000-04700
Plan Check / Job No.
B23LA21683
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan. Proposed second story addition to existing SFD. ***SPRINKLERED PER NFPA 13D***
Permit Issued
Issued on 5/21/2024
Issuing Office
Current Status
CofO Issued on 1/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 MARCELA FRANQUEZ
Corrections Issued 11/26/2023 MICHAEL LOPEZ
Quality Review Completed 11/29/2023 PRANITA SHAH
Applicant returned to address corrections 1/19/2024 MICHAEL LOPEZ
Applicant returned to address corrections 4/3/2024 MICHAEL LOPEZ
Plan Check Approved 5/10/2024 MARCELA FRANQUEZ
Issued 5/21/2024 APPLICANT
CofO in Progress 1/21/2026 BRIAN SULLIVAN
Permit Finaled 1/21/2026 DEROLD HAUFF
CofO Issued 1/21/2026 DEROLD HAUFF
Permit Finaled 1/21/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/8/2023 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/8/2023 EDGAR ALCARAZ
Grading Pre-Inspection Cleared 1/22/2024 MICHAEL LOPEZ
Hydrant and Access approval Cleared 1/27/2024 KURT CORRAL
Private sewage disp. approval Cleared 3/1/2024 MICHAEL TEMPLE
Specific Plan Cleared 4/25/2024 JUDE HERNANDEZ
Specific Plan Cleared 4/25/2024 JUDE HERNANDEZ

Contact Information

Architect Asamoah,, B Kwesi; Lic. No.: C36558 850 ROSE AVENUE      VENICE, CA 90291
Architect Glynn,, Britton Hefner; Lic. No.: NA33548       ,
Contractor Glynn Designbuild Inc; Lic. No.: 841188-B       ,

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/29/2024 Partial Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 8/13/2024 Conditional Approval ROY SPAULDING
Deputy Drilled-In Anchors 9/20/2024 Conditional Approval BRIAN SULLIVAN
Deputy Steel/Welding 9/23/2024 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval BRIAN SULLIVAN
Green Building Rough 10/16/2024 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 10/16/2024 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 2/12/2025 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 2/12/2025 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 2/18/2025 Approved BRIAN SULLIVAN
HVAC-Rough 2/18/2025 Approved BRIAN SULLIVAN
PLUMBING-Rough 2/18/2025 Conditional Approval BRIAN SULLIVAN
Shower Pan 2/18/2025 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 4/8/2025 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 4/8/2025 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 4/14/2025 Approved ROY SPAULDING
BUILDING-Rough-Frame 5/27/2025 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 5/30/2025 Approved BRIAN SULLIVAN
Green Building Rough 5/30/2025 Approved BRIAN SULLIVAN
Insulation 5/30/2025 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 5/30/2025 Approved BRIAN SULLIVAN
Wood Frame 5/30/2025 Approved BRIAN SULLIVAN
Drywall Nailing 6/17/2025 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 6/17/2025 Approved BRIAN SULLIVAN
Underground Mechanical 11/4/2025 Partial Approval ROY SPAULDING
ELECTRICAL-Final 12/2/2025 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 12/2/2025 Approved CRAIG VAUGHAN
Gas Test 12/4/2025 Approved BRIAN SULLIVAN
PLUMBING-Final 12/4/2025 Not Ready for Inspection BRIAN SULLIVAN
Final 12/31/2025 Not Ready for Inspection ROY SPAULDING
Footing/Foundation/Slab 12/31/2025 Not Ready for Inspection ROY SPAULDING
Gas Test 12/31/2025 Not Ready for Inspection ROY SPAULDING
Green Building Final 12/31/2025 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 12/31/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 12/31/2025 Not Ready for Inspection ROY SPAULDING
Gas Test 1/5/2026 Not Ready for Inspection CRAIG VAUGHAN
Final 1/9/2026 Corrections Issued BRIAN SULLIVAN
Final 1/20/2026 OK to Issue CofO BRIAN SULLIVAN
Footing/Foundation/Slab 1/20/2026 Approved BRIAN SULLIVAN
Gas Test 1/20/2026 Approved BRIAN SULLIVAN
Green Building Final 1/20/2026 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 1/20/2026 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 1/20/2026 Approved BRIAN SULLIVAN