1534 W 221ST ST 90501
Certificate Information: 1534 W 221ST ST 90501
- Application / Permit
- 23014-10000-04699
- Plan Check / Job No.
- B23LA21678
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: Detached 1-Story Garage Conversion to ADU and Addition per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 11/9/2024
- Issuing Office
- Current Status
- CofO Issued on 12/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2023 | DAVID CASTILLO |
| Corrections Issued | 11/20/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 3/20/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/5/2024 | DAVID CASTILLO |
| Plan Check Approved | 10/22/2024 | CAROLEAN BASMA |
| Issued | 11/9/2024 | APPLICANT |
| CofO in Progress | 12/11/2025 | EUGENE CASSIDY |
| Permit Finaled | 12/15/2025 | ANSON MAGLASANG |
| CofO Issued | 12/15/2025 | ANSON MAGLASANG |
| Permit Finaled | 12/15/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 3/13/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 4/10/2024 | JILVER MAZARIEGOS |
| Address approval | Cleared | 6/26/2024 | KHAING AYE |
| Sewer availability | Cleared | 6/26/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2024 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 28531 PALOS VERDES DR EAST RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/7/2025 | Approved | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 4/9/2025 | Partial Approval | EUGENE CASSIDY |
| METHANE-Rough | 4/9/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/9/2025 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 4/15/2025 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 4/15/2025 | Corrections Issued | EUGENE CASSIDY |
| Sewer | 4/15/2025 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 4/17/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/17/2025 | Partial Approval | EUGENE CASSIDY |
| Sewer | 4/17/2025 | Partial Approval | EUGENE CASSIDY |
| Sewer | 4/24/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 5/1/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/15/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/15/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/15/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 5/20/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/20/2025 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 5/20/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/27/2025 | Approved | EUGENE CASSIDY |
| Shower Pan | 5/27/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 5/29/2025 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 7/10/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/22/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/22/2025 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/22/2025 | Approved | EUGENE CASSIDY |
| HVAC-Final | 7/22/2025 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 7/22/2025 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 7/22/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 7/22/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 7/22/2025 | Approved | EUGENE CASSIDY |
| Final | 11/26/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/11/2025 | Approved | EUGENE CASSIDY |
| Final | 12/11/2025 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 12/15/2025 | Approved | EUGENE CASSIDY |