523 N LARCHMONT BLVD 90004

Certificate Information: 523 N LARCHMONT BLVD 90004

Application / Permit
23014-10000-04697
Plan Check / Job No.
B23LA21667
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Veterinary Clinic
Work Description
CHANGE OF USE FROM EXISTING DWELLING TO VETERINARIAN CLINIC, INCLDUING NEW 880 SQFT ADDITION.
Permit Issued
Issued on 12/3/2024
Issuing Office
Current Status
CofO Issued on 9/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 PETER MOSESIAN
Assigned to Zoning Architect 12/1/2023 PETER MOSESIAN
Corrections Issued 12/3/2023 PETER MOSESIAN
Quality Review Completed 12/7/2023 OMID HEDAYAT
Applicant returned to address corrections 6/17/2024 PETER MOSESIAN
Applicant returned to address corrections 8/13/2024 PETER MOSESIAN
Plan Check Approved 11/27/2024 PETER MOSESIAN
Issued 12/3/2024 APPLICANT
CofO in Progress 7/22/2025 TIMOTHY POWELL
Permit Finaled 9/3/2025 ERNESTO CORRAL
CofO Issued 9/3/2025 ERNESTO CORRAL
Permit Finaled 9/3/2025 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 12/19/2023 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 3/22/2024 DAVID LOPEZ
Sewer availability Cleared 3/22/2024 DAVID LOPEZ
Green Code Cleared 5/9/2024 AARON COSTA
Low Impact Development (LID) Cleared 7/31/2024 JASMIN ASHLEY
Roof/Waste drainage to street Cleared 8/8/2024 CELINA MORENO
Zoning Plan Check Cleared 8/13/2024 Lawrence Quirante
DAS Clearance Cleared 11/5/2024 Lawrence Quirante
Hold Cleared 1/3/2025 MARIA VENDIVIL

Contact Information

Architect Sheldon,, Geoffrey; Lic. No.: C33374 2201 LITTLE LAS FLORES ROAD      TOPANGA, CA 90290
Contractor Dpt Inc; Lic. No.: 950423-B       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Zhou,, Gangyi; Lic. No.: E18959 26439 RANCHO PKWY S STE 120      LAKE FOREST, CA 92630

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/10/2025 Partial Approval TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Partial Inspection TIMOTHY POWELL
Green Building Rough 3/10/2025 Not Ready for Inspection TIMOTHY POWELL
METHANE-Rough 3/10/2025 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 3/10/2025 Partial Inspection TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Partial Inspection TIMOTHY POWELL
Green Building Rough 3/14/2025 Not Ready for Inspection TIMOTHY POWELL
METHANE-Rough 3/14/2025 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 3/14/2025 Partial Inspection TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Partial Approval TIMOTHY POWELL
Green Building Rough 3/19/2025 Not Ready for Inspection TIMOTHY POWELL
METHANE-Rough 3/19/2025 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 3/19/2025 Partial Approval TIMOTHY POWELL
Insulation 3/26/2025 Approved TIMOTHY POWELL
Interior/Exterior Lathing 3/26/2025 Approved TIMOTHY POWELL
Drywall Nailing 4/1/2025 Partial Approval TIMOTHY POWELL
Green Building Rough 4/1/2025 Not Ready for Inspection TIMOTHY POWELL
Pre-Inspection 5/9/2025 Approved TIMOTHY POWELL
Drywall Nailing 7/2/2025 Conditional Approval DAVID BURKHEAD
Final 7/2/2025 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 7/2/2025 Approved DAVID BURKHEAD
Green Building Final 7/2/2025 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/2/2025 Not Ready for Inspection DAVID BURKHEAD
METHANE-Barrier 7/2/2025 Approved DAVID BURKHEAD
METHANE-Final 7/2/2025 Approved DAVID BURKHEAD
METHANE-Rough 7/2/2025 Approved DAVID BURKHEAD
METHANE-Subgrade 7/2/2025 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 7/2/2025 Approved DAVID BURKHEAD
Wood Frame 7/2/2025 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 7/8/2025 Approved TIMOTHY POWELL
Final 7/8/2025 Partial Inspection TIMOTHY POWELL
Green Building Final 7/8/2025 Approved TIMOTHY POWELL
Green Building Rough 7/8/2025 Approved TIMOTHY POWELL
Wood Frame 7/8/2025 Approved TIMOTHY POWELL
Final 7/22/2025 OK to Issue CofO TIMOTHY POWELL