523 N LARCHMONT BLVD 90004
Certificate Information: 523 N LARCHMONT BLVD 90004
- Application / Permit
- 23014-10000-04697
- Plan Check / Job No.
- B23LA21667
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Veterinary Clinic
- Work Description
- CHANGE OF USE FROM EXISTING DWELLING TO VETERINARIAN CLINIC, INCLDUING NEW 880 SQFT ADDITION.
- Permit Issued
- Issued on 12/3/2024
- Issuing Office
- Current Status
- CofO Issued on 9/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | PETER MOSESIAN |
| Assigned to Zoning Architect | 12/1/2023 | PETER MOSESIAN |
| Corrections Issued | 12/3/2023 | PETER MOSESIAN |
| Quality Review Completed | 12/7/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/17/2024 | PETER MOSESIAN |
| Applicant returned to address corrections | 8/13/2024 | PETER MOSESIAN |
| Plan Check Approved | 11/27/2024 | PETER MOSESIAN |
| Issued | 12/3/2024 | APPLICANT |
| CofO in Progress | 7/22/2025 | TIMOTHY POWELL |
| Permit Finaled | 9/3/2025 | ERNESTO CORRAL |
| CofO Issued | 9/3/2025 | ERNESTO CORRAL |
| Permit Finaled | 9/3/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 12/19/2023 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 3/22/2024 | DAVID LOPEZ |
| Green Code | Cleared | 5/9/2024 | AARON COSTA |
| Low Impact Development (LID) | Cleared | 7/31/2024 | JASMIN ASHLEY |
| Roof/Waste drainage to street | Cleared | 8/8/2024 | CELINA MORENO |
| Zoning Plan Check | Cleared | 8/13/2024 | Lawrence Quirante |
| DAS Clearance | Cleared | 11/5/2024 | Lawrence Quirante |
| Hold | Cleared | 1/3/2025 | MARIA VENDIVIL |
Contact Information
| Architect | Sheldon,, Geoffrey; Lic. No.: C33374 | 2201 LITTLE LAS FLORES ROAD TOPANGA, CA 90290 |
| Contractor | Dpt Inc; Lic. No.: 950423-B | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Zhou,, Gangyi; Lic. No.: E18959 | 26439 RANCHO PKWY S STE 120 LAKE FOREST, CA 92630 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/10/2025 | Partial Approval | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Partial Inspection | TIMOTHY POWELL |
| Green Building Rough | 3/10/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| METHANE-Rough | 3/10/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 3/10/2025 | Partial Inspection | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Partial Inspection | TIMOTHY POWELL |
| Green Building Rough | 3/14/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| METHANE-Rough | 3/14/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 3/14/2025 | Partial Inspection | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 3/19/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| METHANE-Rough | 3/19/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 3/19/2025 | Partial Approval | TIMOTHY POWELL |
| Insulation | 3/26/2025 | Approved | TIMOTHY POWELL |
| Interior/Exterior Lathing | 3/26/2025 | Approved | TIMOTHY POWELL |
| Drywall Nailing | 4/1/2025 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 4/1/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Pre-Inspection | 5/9/2025 | Approved | TIMOTHY POWELL |
| Drywall Nailing | 7/2/2025 | Conditional Approval | DAVID BURKHEAD |
| Final | 7/2/2025 | Not Ready for Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 7/2/2025 | Approved | DAVID BURKHEAD |
| Green Building Final | 7/2/2025 | Not Ready for Inspection | DAVID BURKHEAD |
| Green Building Rough | 7/2/2025 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Barrier | 7/2/2025 | Approved | DAVID BURKHEAD |
| METHANE-Final | 7/2/2025 | Approved | DAVID BURKHEAD |
| METHANE-Rough | 7/2/2025 | Approved | DAVID BURKHEAD |
| METHANE-Subgrade | 7/2/2025 | Approved | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | DAVID BURKHEAD |
| Smoke Detectors | 7/2/2025 | Approved | DAVID BURKHEAD |
| Wood Frame | 7/2/2025 | Not Ready for Inspection | DAVID BURKHEAD |
| Drywall Nailing | 7/8/2025 | Approved | TIMOTHY POWELL |
| Final | 7/8/2025 | Partial Inspection | TIMOTHY POWELL |
| Green Building Final | 7/8/2025 | Approved | TIMOTHY POWELL |
| Green Building Rough | 7/8/2025 | Approved | TIMOTHY POWELL |
| Wood Frame | 7/8/2025 | Approved | TIMOTHY POWELL |
| Final | 7/22/2025 | OK to Issue CofO | TIMOTHY POWELL |