344 S ORANGE DR 90036
Certificate Information: 344 S ORANGE DR 90036
- Application / Permit
- 23014-10000-04676
- Plan Check / Job No.
- B23LA21555
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN PROPOSED IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING - PER ENGINEER
- Permit Issued
- Issued on 12/28/2023
- Issuing Office
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 11/18/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 12/13/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 12/19/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 12/22/2023 | MICHAEL LOPEZ |
| Issued | 12/28/2023 | APPLICANT |
| CofO in Progress | 2/20/2026 | RONNIE MINDANAO |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2023 | JEANIE LAM |
| Sewer availability | Cleared | 11/21/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 12/15/2023 | JEANIE LAM |
Contact Information
| Contractor | Huberman Michael; Lic. No.: 464070-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 3/11/2024 | Conditional Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 3/20/2024 | Conditional Approval | RONNIE MINDANAO |
| METHANE-Barrier | 3/20/2024 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 3/20/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 6/20/2024 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 6/20/2024 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 7/10/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 7/10/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 7/10/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 7/23/2024 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 7/29/2024 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 7/31/2024 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 2/4/2025 | Partial Inspection | RONNIE MINDANAO |
| Final | 2/4/2025 | Partial Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 2/4/2025 | Partial Inspection | RONNIE MINDANAO |
| Green Building Final | 2/4/2025 | Partial Inspection | RONNIE MINDANAO |
| Green Building Rough | 2/4/2025 | Partial Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 2/4/2025 | Partial Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/12/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 11/12/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 11/12/2025 | Conditional Approval | RONNIE MINDANAO |
| Green Building Final | 11/12/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 11/12/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 11/12/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 12/2/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 12/2/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/2/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 12/2/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 12/2/2025 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 12/2/2025 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/3/2025 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 12/3/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 12/3/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 12/3/2025 | Approved | RONNIE MINDANAO |
| Insulation | 12/3/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 12/3/2025 | SGSOV Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 12/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 12/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 12/24/2025 | Approved | RONNIE MINDANAO |
| Green Building Final | 12/24/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 12/24/2025 | Approved | RONNIE MINDANAO |
| Smoke Detectors | 12/24/2025 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 2/3/2026 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 2/3/2026 | Approved | RONNIE MINDANAO |
| Final | 2/3/2026 | OK to Issue CofO | RONNIE MINDANAO |
| Insulation | 2/3/2026 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 2/3/2026 | Approved | RONNIE MINDANAO |
| Smoke Detectors | 2/3/2026 | Approved | RONNIE MINDANAO |