4763 E FRIEDA DR 90065
Certificate Information: 4763 E FRIEDA DR 90065
- Application / Permit
- 23014-10000-04640
- Plan Check / Job No.
- B23LA21401
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert (E) garage to ADU with addition per Ordinance LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2023 | NEHEMIAS RAMOS |
| Corrections Issued | 11/16/2023 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 11/30/2023 | NEHEMIAS RAMOS |
| Plan Check Approved | 2/20/2024 | NEHEMIAS RAMOS |
| Issued | 5/7/2024 | APPLICANT |
| CofO in Progress | 4/14/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 4/17/2025 | DEROLD HAUFF |
| CofO Issued | 4/17/2025 | DEROLD HAUFF |
| Permit Finaled | 4/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2023 | JUSTIN BICOL |
| Grading Pre-Inspection | Cleared | 11/21/2023 | ALEXANDER HELFER |
| Roof/Waste drainage to street | Cleared | 11/21/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 11/21/2023 | JUSTIN BICOL |
| Specific Plan | Cleared | 11/29/2023 | PABLO ESTRADA |
| BHO/Hillside ordinance | Cleared | 11/30/2023 | JUSTIN BICOL |
| Construction near power lines | Cleared | 2/12/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/14/2024 | Partial Inspection | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 5/24/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/24/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/28/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/24/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/12/2024 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 7/12/2024 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/5/2024 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/5/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 8/19/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 8/19/2024 | Partial Inspection | ALEX COLIN |
| Wood Frame | 8/19/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/23/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 8/23/2024 | Approved | THOMAS LOGRASSO |
| Wood Frame | 8/23/2024 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/30/2024 | Approved | LUIS CASTRO |
| Insulation | 8/30/2024 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 8/30/2024 | Approved | LUIS CASTRO |
| Drywall Nailing | 9/9/2024 | Approved | ROY SPAULDING |
| Shower Pan | 9/19/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/25/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 3/14/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 3/14/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 3/14/2025 | Corrections Issued | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 3/20/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 3/20/2025 | Approved | NICHOLAS LOPEZ |
| Final | 3/20/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 3/20/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Green Building Rough | 3/20/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 3/20/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 3/20/2025 | Approved | NICHOLAS LOPEZ |
| Final | 4/10/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 4/10/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Final | 4/14/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Approved | NICHOLAS LOPEZ |