131 W AVENUE 43 90065
Certificate Information: 131 W AVENUE 43 90065
- Application / Permit
- 23014-10000-04616
- Plan Check / Job No.
- B23LA21340
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 411 sq ft Addition with 71 sq ft new covered front porch and remodel to existing 1-story single family dwelling. "COMPLY WITH DEPARTMENT ORDER effective date 11/06/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 3/21/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2023 | AUNG SOE |
| Corrections Issued | 11/16/2023 | VICTOR CHEN |
| Building Plans Picked Up | 12/8/2023 | APPLICANT |
| Plan Check Approved | 3/20/2024 | MINA HABILI |
| Issued | 3/21/2024 | APPLICANT |
| CofO in Progress | 1/17/2025 | GLEN RAND |
| Permit Finaled | 2/18/2025 | SHAWN ESHBACH |
| CofO Issued | 2/18/2025 | SHAWN ESHBACH |
| Permit Finaled | 2/18/2025 | SHAWN ESHBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/18/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2023 | ADRIAN SANCHEZ |
| Metro Rail approval | Cleared | 12/21/2023 | JENNIFER SU |
| HPOZ | Cleared | 3/12/2024 | MICAELA TORRES-GIL |
| Grading Pre-Inspection | Cleared | 3/18/2024 | SERGIO VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| EDMUND LUM, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUCIANO GAUNA, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAIME RIOS, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDEY CHAPARRO, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN BARNES, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| PATRICK LIEBREGT, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| GLEN RAND, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAWN ESHBACH, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| GABRIEL HERRERA, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/8/2024 | No Access for Inspection | LUCIANO GAUNA |
| Excavation/Setback/Form/Re-Bar | 5/10/2024 | Approved | GABRIEL HERRERA |
| BUILDING-Rough-Frame | 5/21/2024 | Conditional Approval | LUCIANO GAUNA |
| Green Building Rough | 5/21/2024 | Conditional Approval | LUCIANO GAUNA |
| MERV13>=Rough | 5/21/2024 | Conditional Approval | LUCIANO GAUNA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Approved | GABRIEL HERRERA |
| Insulation | 5/24/2024 | Approved | GABRIEL HERRERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Corrections Issued | GLEN RAND |
| BUILDING-Rough-Frame | 7/9/2024 | Corrections Issued | HAGOP BADOSSIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Partial Approval | HAGOP BADOSSIAN |
| Rough-Elec/Plmb/HVAC | 7/23/2024 | Corrections Issued | GLEN RAND |
| Rough-Elec/Plmb/HVAC | 7/26/2024 | Corrections Issued | GLEN RAND |
| HVAC-Rough | 8/22/2024 | Corrections Issued | GLEN RAND |
| PLUMBING-Rough | 8/22/2024 | Corrections Issued | GLEN RAND |
| HVAC-Rough | 8/29/2024 | Corrections Issued | GLEN RAND |
| PLUMBING-Rough | 8/29/2024 | Corrections Issued | GLEN RAND |
| HVAC-Rough | 9/4/2024 | Approved | GLEN RAND |
| PLUMBING-Rough | 9/4/2024 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 9/9/2024 | Not Ready for Inspection | GLEN RAND |
| Deputy Drilled-In Anchors | 9/9/2024 | Approved | GLEN RAND |
| ELECTRICAL-Rough | 9/9/2024 | Approved | GLEN RAND |
| Green Building Rough | 9/9/2024 | Not Ready for Inspection | GLEN RAND |
| MERV13>=Rough | 9/9/2024 | Not Ready for Inspection | GLEN RAND |
| ELECTRICAL-Rough | 9/12/2024 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Rough | 9/17/2024 | Approved | GLEN RAND |
| Shower Pan | 10/1/2024 | Approved | GLEN RAND |
| Interior/Exterior Lathing | 10/8/2024 | Partial Approval | GLEN RAND |
| Interior/Exterior Lathing | 10/11/2024 | Corrections Issued | GLEN RAND |
| Interior/Exterior Lathing | 10/16/2024 | Approved | GLEN RAND |
| Special/Order Compliance | 11/13/2024 | Corrections Issued | GLEN RAND |
| Special/Order Compliance | 11/15/2024 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 12/9/2024 | Conditional Approval | GLEN RAND |
| Final | 12/9/2024 | Not Ready for Inspection | GLEN RAND |
| Footing/Foundation/Slab | 12/9/2024 | Approved | GLEN RAND |
| Green Building Final | 12/9/2024 | Approved | GLEN RAND |
| Green Building Rough | 12/9/2024 | Approved | GLEN RAND |
| MERV13>=Final | 12/9/2024 | Not Ready for Inspection | GLEN RAND |
| MERV13>=Rough | 12/9/2024 | Corrections Issued | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Not Ready | GLEN RAND |
| Smoke Detectors | 12/9/2024 | Not Ready for Inspection | GLEN RAND |
| BUILDING-Rough-Frame | 12/13/2024 | Approved | GLEN RAND |
| Final | 12/13/2024 | Corrections Issued | GLEN RAND |
| MERV13>=Rough | 12/13/2024 | Approved | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 12/13/2024 | SGSOV Not Ready | GLEN RAND |
| Smoke Detectors | 12/13/2024 | Approved | GLEN RAND |
| Final | 12/27/2024 | Conditional Approval | GLEN RAND |
| MERV13>=Final | 12/27/2024 | Approved | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 12/27/2024 | SGSOV Approved | GLEN RAND |
| Final | 1/13/2025 | Corrections Issued | GLEN RAND |
| Service/Power Release | 1/16/2025 | Approved | GLEN RAND |
| Final | 1/17/2025 | OK to Issue CofO | GLEN RAND |