GROUND FLOOR ADDITION, SECOND FLOOR ADDITION, AND REMODEL OF (E) 1-STORY SFD WITH ATTACHED 2-CAR GARAGE. *** SFD TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THRU OUT***
Permit Issued
Issued on 8/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 VIVIAN LAO
Corrections Issued 11/20/2023 CRYSTEL MAALOUF
Quality Review Completed 11/30/2023 KEN GILL
Building Plans Picked Up 12/13/2023 APPLICANT
Applicant returned to address corrections 6/4/2024 VIVIAN LAO
Plan Check Approved 6/26/2024 VIVIAN LAO
Issued 8/19/2024 APPLICANT
CofO in Progress 12/10/2025 CHRISTOPHE COCHRAN
Permit Finaled 1/2/2026 RUBEN SALAS
CofO Issued 1/2/2026 RUBEN SALAS
Permit Finaled 1/2/2026 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/18/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/18/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/18/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/18/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/18/2023 CARLOS AGUILERA
Watercourse Cleared 12/18/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/19/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/20/2023 CARLOS AGUILERA
Sewer availability Cleared 12/20/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/16/2024 GILBERT URREA
Construction near power lines Cleared 4/25/2024 RIDWAN HARDY
GPI Written Notices Cleared 6/4/2024 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 6/4/2024 CRYSTEL MAALOUF

Contact Information

Architect Scrafano,, Elissa F; Lic. No.: C26071 163 N SYCAMORE      LOS ANGELES, CA 90036
Contractor Lanai Construction Inc; Lic. No.: 967986-B 5351 DE ROJA AVENUE      WOODLAND HILLS, CA 91364
Engineer Zangoli,, Fabio; Lic. No.: S6191 13245 FIJI WY UNIT J      MARINA DEL REY, CA 90292

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/5/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Pre-Inspection 9/5/2024 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 9/6/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/18/2024 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 9/24/2024 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/8/2024 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 10/9/2024 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 12/13/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 1/10/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 1/10/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/10/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 2/10/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/20/2025 Partial Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/20/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 3/20/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 3/20/2025 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 3/20/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 4/3/2025 Approved CHRISTOPHE COCHRAN
Insulation 4/3/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 4/4/2025 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 4/14/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 4/17/2025 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 5/1/2025 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Rough 5/1/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 5/1/2025 Approved CHRISTOPHE COCHRAN
Shower Pan 5/1/2025 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/6/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 5/6/2025 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 5/16/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/16/2025 Corrections Issued CHRISTOPHE COCHRAN
Insulation 5/22/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/22/2025 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 6/2/2025 Approved CHRISTOPHE COCHRAN
Final 10/9/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 10/9/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 10/9/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 12/9/2025 Approved CHRISTOPHE COCHRAN
Final 12/9/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 12/9/2025 Approved CHRISTOPHE COCHRAN
Smoke Detectors 12/9/2025 Approved CHRISTOPHE COCHRAN
Final 12/10/2025 OK to Issue CofO CHRISTOPHE COCHRAN