4030 N DIXIE CANYON AVE 91423
Certificate Information: 4030 N DIXIE CANYON AVE 91423
- Application / Permit
- 23014-10000-04615
- Plan Check / Job No.
- B23LA21338
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION, SECOND FLOOR ADDITION, AND REMODEL OF (E) 1-STORY SFD WITH ATTACHED 2-CAR GARAGE. *** SFD TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THRU OUT***
- Permit Issued
- Issued on 8/19/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | VIVIAN LAO |
| Corrections Issued | 11/20/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 11/30/2023 | KEN GILL |
| Building Plans Picked Up | 12/13/2023 | APPLICANT |
| Applicant returned to address corrections | 6/4/2024 | VIVIAN LAO |
| Plan Check Approved | 6/26/2024 | VIVIAN LAO |
| Issued | 8/19/2024 | APPLICANT |
| CofO in Progress | 12/10/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 1/2/2026 | RUBEN SALAS |
| CofO Issued | 1/2/2026 | RUBEN SALAS |
| Permit Finaled | 1/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/18/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/18/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/18/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/18/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/18/2023 | CARLOS AGUILERA |
| Watercourse | Cleared | 12/18/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/19/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/20/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/16/2024 | GILBERT URREA |
| Construction near power lines | Cleared | 4/25/2024 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 6/4/2024 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 6/4/2024 | CRYSTEL MAALOUF |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Lanai Construction Inc; Lic. No.: 967986-B | 5351 DE ROJA AVENUE WOODLAND HILLS, CA 91364 |
| Engineer | Zangoli,, Fabio; Lic. No.: S6191 | 13245 FIJI WY UNIT J MARINA DEL REY, CA 90292 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/5/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Pre-Inspection | 9/5/2024 | Approved | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 9/6/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/18/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 9/24/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 10/8/2024 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 10/9/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 12/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 1/10/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 1/10/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 2/10/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/10/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/13/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/20/2025 | Partial Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 3/20/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/20/2025 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 3/20/2025 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 3/20/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 4/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 4/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/4/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Drywall Nailing | 4/14/2025 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 4/17/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/1/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 5/1/2025 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/1/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 5/1/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/6/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/16/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 5/16/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Insulation | 5/22/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 5/22/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 10/9/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 10/9/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 10/9/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 12/9/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/9/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 12/9/2025 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/9/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/10/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |