1375 N WETHERLY DR 90069
Certificate Information: 1375 N WETHERLY DR 90069
- Application / Permit
- 23014-10000-04585
- Plan Check / Job No.
- B23LA21154
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (123 S.F) ADDITION TO THE (E) SINGLE FAMILY DWELLING WITH ATTACHED CARPORT. REMOVE AND REPLACE THE (E)ROOF OVER THE NEW CONCRETE RAISED PATIO THAT CONNECTS WITH THE EXISTING CARPORT ROOF AND INTERIOR REMODEL TO ADD CLOSET AT FRONT ENTRY.
- Permit Issued
- Issued on 1/12/2024
- Issuing Office
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 11/15/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 11/23/2023 | SARKIS HARABEDIAN |
| Issued | 1/12/2024 | APPLICANT |
| CofO in Progress | 5/6/2025 | ROY SPAULDING |
| CofO Issued | 5/7/2025 | DEROLD HAUFF |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/16/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2023 | ARNULFO CHAMU |
| Grading Pre-Inspection | Cleared | 11/23/2023 | DANIEL ABRAMYAN |
Contact Information
| Contractor | Willow Group Inc The; Lic. No.: 721043-B | 23974 CRAFTSMAN ROAD CALABASAS, CA 91302 |
| Engineer | Schaefer,, Jeffrey; Lic. No.: C91734 | 3325 E 4TH ST LONG BEACH, CA 90814 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/26/2024 | Not Ready for Inspection | ROY SPAULDING |
| Pre-Inspection | 2/26/2024 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 3/11/2024 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/10/2024 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/23/2024 | Partial Approval | ROY SPAULDING |
| PLUMBING-Rough | 5/6/2024 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 5/8/2024 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 5/14/2024 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/10/2024 | Partial Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2024 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/11/2024 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/11/2024 | Approved | RAUL BARAJAS |
| Insulation | 6/17/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/17/2024 | Approved | RAUL BARAJAS |
| Shower Pan | 6/17/2024 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/20/2024 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/24/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 8/20/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 9/3/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 9/5/2024 | Approved | RAUL BARAJAS |
| Pre-Inspection | 11/6/2024 | Corrections Issued | RAUL BARAJAS |
| Final | 3/6/2025 | Conditional Approval | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 3/6/2025 | Approved | ROY SPAULDING |
| Final | 5/6/2025 | OK to Issue CofO | ROY SPAULDING |