4532 N MAMMOTH AVE 91423

Certificate Information: 4532 N MAMMOTH AVE 91423

Application / Permit
23014-10000-04583
Plan Check / Job No.
B23LA21148
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) Garage to ADU with addition per LAMC 12.22 A.33(c)-(d)
Permit Issued
Issued on 5/14/2024
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2023 APPLICANT
Assigned to Plan Check Engineer 11/22/2023 NEHEMIAS RAMOS
Corrections Issued 11/24/2023 NEHEMIAS RAMOS
Plan Check Approved 3/2/2024 NEHEMIAS RAMOS
Issued 5/14/2024 APPLICANT
CofO in Progress 3/16/2026 MISAEL ESPARZA
Permit Finaled 4/2/2026 RUBEN SALAS
CofO Issued 4/2/2026 RUBEN SALAS
Permit Finaled 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 2/12/2024 TINA MIRANDA
Address approval Cleared 2/22/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/22/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 2/22/2024 CARLOS RAMIREZ
Sewer availability Cleared 2/22/2024 CARLOS RAMIREZ
ZI Cleared 2/26/2024 ASHLEY RODARTE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/26/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 8/28/2025 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 9/2/2025 Approved MISAEL ESPARZA
Footing/Foundation/Slab 9/2/2025 Approved MISAEL ESPARZA
Sewer 9/11/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/19/2025 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 9/19/2025 Approved MISAEL ESPARZA
Green Building Rough 9/19/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 9/19/2025 Corrections Issued MISAEL ESPARZA
MERV13>=Rough 9/19/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 9/19/2025 Approved MISAEL ESPARZA
Underground Mechanical 9/19/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/24/2025 Approved MISAEL ESPARZA
HVAC-Rough 9/24/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/24/2025 Partial Approval MISAEL ESPARZA
Insulation 9/30/2025 Approved MISAEL ESPARZA
Drywall Nailing 10/3/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 10/17/2025 Approved CHRISTOPHER MORFIN
Shower Pan 10/17/2025 Approved CHRISTOPHER MORFIN
BUILDING-Rough-Frame 3/6/2026 Approved MISAEL ESPARZA
Final 3/6/2026 Corrections Issued MISAEL ESPARZA
Green Building Final 3/6/2026 Approved MISAEL ESPARZA
Green Building Rough 3/6/2026 Approved MISAEL ESPARZA
MERV13>=Final 3/6/2026 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Not Required MISAEL ESPARZA
Smoke Detectors 3/6/2026 Approved MISAEL ESPARZA
Final 3/13/2026 OK to Issue CofO MISAEL ESPARZA