14307 W MARTHA ST 91401

Certificate Information: 14307 W MARTHA ST 91401

Application / Permit
23014-10000-04578
Plan Check / Job No.
B23LA21139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRREGULARLY SHAPED ADDITION (593 SF) TO REAR OF SFD, NEW REAR COVERED PORCH (100 SF), NEW FOYER ADDITION (9 SF), NEW FRONT COVERED PORCH (32 SF), AND REMODEL OF EXISTING BATHROOM AND KITCHEN. ALL WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 3/1/2024
Issuing Office
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/13/2023 JOSEPH RAFOLS
Corrections Issued 11/14/2023 JOSEPH RAFOLS
Applicant returned to address corrections 2/2/2024 MADISON ODELL
Applicant returned to address corrections 2/10/2024 MADISON ODELL
Applicant returned to address corrections 2/22/2024 MADISON ODELL
Plan Check Approved 2/28/2024 MADISON O'DELL
Issued 3/1/2024 APPLICANT
CofO in Progress 4/29/2025 RYAN SALAZAR
Permit Finaled 6/5/2025 RUBEN SALAS
Permit Finaled 6/5/2025 RUBEN SALAS
CofO Issued 6/5/2025 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 11/14/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/15/2023 CARLOS RAMIREZ
Low Impact Development (LID) Cleared 1/26/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 1/27/2024 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Kiledjian,, George Zohrab; Lic. No.: NA74761       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2024 Approved RYAN SALAZAR
Underground Mechanical 5/1/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 6/17/2024 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 7/24/2024 Approved MICHEL ABAJAN
HVAC-Rough 7/24/2024 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 7/24/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/6/2024 Approved RYAN SALAZAR
Insulation 8/19/2024 Approved RYAN SALAZAR
Shower Pan 8/19/2024 Approved RYAN SALAZAR
Drywall Nailing 9/5/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/5/2024 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 9/10/2024 Approved ROBERT GOLD
ELECTRICAL-Final 1/8/2025 Not Ready for Inspection JOSE AVILA
HVAC-Final 1/8/2025 Not Ready for Inspection JOSE AVILA
PLUMBING-Final 1/8/2025 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Final 1/14/2025 Approved RYAN SALAZAR
HVAC-Final 1/14/2025 Approved RYAN SALAZAR
PLUMBING-Final 1/14/2025 Approved RYAN SALAZAR
Final 4/28/2025 OK to Issue CofO RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 4/28/2025 Approved RYAN SALAZAR