14307 W MARTHA ST 91401
Certificate Information: 14307 W MARTHA ST 91401
- Application / Permit
- 23014-10000-04578
- Plan Check / Job No.
- B23LA21139
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRREGULARLY SHAPED ADDITION (593 SF) TO REAR OF SFD, NEW REAR COVERED PORCH (100 SF), NEW FOYER ADDITION (9 SF), NEW FRONT COVERED PORCH (32 SF), AND REMODEL OF EXISTING BATHROOM AND KITCHEN. ALL WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 3/1/2024
- Issuing Office
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2023 | JOSEPH RAFOLS |
| Corrections Issued | 11/14/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 2/2/2024 | MADISON ODELL |
| Applicant returned to address corrections | 2/10/2024 | MADISON ODELL |
| Applicant returned to address corrections | 2/22/2024 | MADISON ODELL |
| Plan Check Approved | 2/28/2024 | MADISON O'DELL |
| Issued | 3/1/2024 | APPLICANT |
| CofO in Progress | 4/29/2025 | RYAN SALAZAR |
| Permit Finaled | 6/5/2025 | RUBEN SALAS |
| Permit Finaled | 6/5/2025 | RUBEN SALAS |
| CofO Issued | 6/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/14/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2023 | CARLOS RAMIREZ |
| Low Impact Development (LID) | Cleared | 1/26/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 1/27/2024 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kiledjian,, George Zohrab; Lic. No.: NA74761 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/17/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 5/1/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/17/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 7/24/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/24/2024 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 7/24/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/6/2024 | Approved | RYAN SALAZAR |
| Insulation | 8/19/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 8/19/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/5/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/5/2024 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/10/2024 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 1/8/2025 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Final | 1/8/2025 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Final | 1/8/2025 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 1/14/2025 | Approved | RYAN SALAZAR |
| HVAC-Final | 1/14/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 1/14/2025 | Approved | RYAN SALAZAR |
| Final | 4/28/2025 | OK to Issue CofO | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/28/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 4/28/2025 | Approved | RYAN SALAZAR |