1214 S FAIRFAX AVE 90019

Certificate Information: 1214 S FAIRFAX AVE 90019

Application / Permit
23014-10000-04575
Plan Check / Job No.
B23LA21114
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
PROPOSED ADDITION TO (E) CHURCH TO CREATE (N) ALTAR AREA & (N) PIPE ORGAN AREA.
Permit Issued
Issued on 8/14/2025
Issuing Office
Metro
Current Status
Issued on 8/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/7/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 MICHAEL LOPEZ
Corrections Issued 11/15/2023 MICHAEL LOPEZ
Assigned to Zoning Architect 11/17/2023 CALEB WONG
Quality Review Completed 12/5/2023 KEN GILL
Building Plans Picked Up 12/5/2023 APPLICANT
Disabled Access Plans Picked Up 12/20/2023 APPLICANT
Applicant returned to address corrections 7/3/2025 MICHAEL LOPEZ
Applicant returned to address corrections 8/8/2025 MICHAEL LOPEZ
Plan Check Approved 8/12/2025 MICHAEL LOPEZ
Issued 8/14/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/6/2023 DAVID LOPEZ
Sewer availability Cleared 12/6/2023 DAVID LOPEZ
Hydrant and Access approval Cleared 1/19/2024 JOHN CONNEALLY
Fire Marshal Fire Life Safety Cleared 2/21/2024 FIRE DEPARTMENT
Green Code Cleared 8/26/2024 MICHAEL LOPEZ
CPC Cleared 1/28/2025 JACQUELINE TORRES
ZA Case Cleared 1/28/2025 JACQUELINE TORRES
Low Impact Development (LID) Cleared 5/20/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 5/28/2025 JEREMY CHOK
Zoning Plan Check Cleared 6/9/2025 MICHAEL LOPEZ
DAS Clearance Cleared 6/13/2025 MICHAEL LOPEZ

Contact Information

Contractor Yireh Construction Inc; Lic. No.: 1089955-B 16108 COMPASS AVE      CHINO, CA 91708
Engineer Kim,, Seung; Lic. No.: S5909 9934 CEDAR CT      CYPRESS, CA 90630

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/20/2025 Approved MARTIN TAVITIAN
Footing/Foundation/Slab 9/18/2025 Partial Approval MARTIN TAVITIAN
METHANE-Barrier 9/18/2025 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Subgrade 9/18/2025 Not Ready for Inspection MARTIN TAVITIAN
Footing/Foundation/Slab 9/19/2025 Partial Approval MARTIN TAVITIAN
METHANE-Barrier 9/19/2025 Partial Approval MARTIN TAVITIAN
METHANE-Subgrade 9/19/2025 Approved MARTIN TAVITIAN
Pre-Inspection 10/16/2025 Partial Approval MARTIN TAVITIAN
Footing/Foundation/Slab 10/20/2025 Partial Approval MARTIN TAVITIAN
METHANE-Barrier 10/20/2025 Not Ready for Inspection MARTIN TAVITIAN
Special/Order Compliance 10/20/2025 Corrections Issued MARTIN TAVITIAN
Green Building Rough 10/31/2025 Approved MARTIN TAVITIAN
METHANE-Rough 10/31/2025 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 10/31/2025 Partial Inspection MARTIN TAVITIAN
METHANE-Rough 11/12/2025 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 11/12/2025 Not Ready for Inspection MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Partial Approval MARTIN TAVITIAN
Footing/Foundation/Slab 11/19/2025 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Rough 11/19/2025 Not Ready for Inspection MARTIN TAVITIAN
Pre-Inspection 11/20/2025 Partial Approval MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 11/24/2025 Partial Approval MARTIN TAVITIAN
METHANE-Rough 12/2/2025 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 12/2/2025 Corrections Issued MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 12/4/2025 Approved MARTIN TAVITIAN
Footing/Foundation/Slab 12/4/2025 Partial Approval MARTIN TAVITIAN
METHANE-Barrier 12/4/2025 Not Ready for Inspection MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 12/5/2025 Corrections Issued RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 12/8/2025 Corrections Issued RONALD JIMENEZ
Footing/Foundation/Slab 12/8/2025 Not Ready for Inspection RONALD JIMENEZ
METHANE-Barrier 12/8/2025 Not Ready for Inspection RONALD JIMENEZ
Special/Order Compliance 12/8/2025 Partial Inspection REGINA MENDEZ
Excavation/Setback/Form/Re-Bar 12/17/2025 Partial Approval MARTIN TAVITIAN
Footing/Foundation/Slab 12/17/2025 Partial Approval MARTIN TAVITIAN
METHANE-Barrier 12/17/2025 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Rough 12/30/2025 Not Ready for Inspection MARTIN TAVITIAN
Special/Order Compliance 12/30/2025 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 12/30/2025 Not Ready for Inspection MARTIN TAVITIAN
Pre-Inspection 12/31/2025 Approved MARTIN TAVITIAN
Special/Order Compliance 12/31/2025 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Rough 1/2/2026 Not Ready for Inspection MARTIN TAVITIAN
Special/Order Compliance 1/2/2026 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 1/2/2026 Partial Approval MARTIN TAVITIAN
Pre-Inspection 1/5/2026 Partial Approval MARTIN TAVITIAN
Pre-Inspection 1/7/2026 Approved MARTIN TAVITIAN
METHANE-Rough 1/13/2026 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 1/13/2026 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Rough 1/16/2026 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 1/16/2026 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 2/10/2026 Not Ready for Inspection MARTIN TAVITIAN
Light Gage Steel Frame 2/13/2026 Partial Approval MARTIN TAVITIAN
Interior/Exterior Lathing 2/18/2026 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Rough 2/18/2026 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Rough 2/19/2026 Not Ready for Inspection MARTIN TAVITIAN
Deputy Methane Barrier 2/20/2026 No Access for Inspection MARTIN TAVITIAN
METHANE-Barrier 2/20/2026 Not Ready for Inspection MARTIN TAVITIAN
Insulation 2/24/2026 Partial Approval CHRISTOPHER BLACKWOOD
Interior/Exterior Lathing 2/24/2026 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 2/25/2026 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 2/25/2026 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Insulation 2/27/2026 Conditional Approval CHRISTOPHER BLACKWOOD
Interior/Exterior Lathing 2/27/2026 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 2/27/2026 Conditional Approval CHRISTOPHER BLACKWOOD
Insulation 3/3/2026 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 3/3/2026 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Insulation 3/4/2026 Partial Approval CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 3/4/2026 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Insulation 3/10/2026 Partial Approval IAN BLINN
Interior/Exterior Lathing 3/10/2026 Partial Approval IAN BLINN
Excavation/Setback/Form/Re-Bar 3/13/2026 Not Ready for Inspection MARTIN TAVITIAN
Footing/Foundation/Slab 3/13/2026 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Barrier 3/13/2026 Not Ready for Inspection MARTIN TAVITIAN
Deputy Methane Barrier 3/17/2026 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 3/17/2026 Approved DARRYL ARNOLD
METHANE-Barrier 3/17/2026 Partial Inspection CHRISTOPHER BLACKWOOD
Excavation/Setback/Form/Re-Bar 3/19/2026 Partial Approval CHRISTOPHER BLACKWOOD
METHANE-Barrier 3/19/2026 Approved CHRISTOPHER BLACKWOOD
Insulation 3/20/2026 Partial Approval JEROME BLACKWOOD
Insulation 3/21/2026 Off-Hour Fees Due
Drywall Nailing 3/23/2026 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 3/23/2026 Partial Approval LUIS CCAMACHO
Drywall Nailing 3/25/2026 Partial Approval ALFREDO LOPEZ