1214 S FAIRFAX AVE 90019
Certificate Information: 1214 S FAIRFAX AVE 90019
- Application / Permit
- 23014-10000-04575
- Plan Check / Job No.
- B23LA21114
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- PROPOSED ADDITION TO (E) CHURCH TO CREATE (N) ALTAR AREA & (N) PIPE ORGAN AREA.
- Permit Issued
- Issued on 8/14/2025
- Issuing Office
- Metro
- Current Status
- Issued on 8/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | MICHAEL LOPEZ |
| Corrections Issued | 11/15/2023 | MICHAEL LOPEZ |
| Assigned to Zoning Architect | 11/17/2023 | CALEB WONG |
| Quality Review Completed | 12/5/2023 | KEN GILL |
| Building Plans Picked Up | 12/5/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 12/20/2023 | APPLICANT |
| Applicant returned to address corrections | 7/3/2025 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/8/2025 | MICHAEL LOPEZ |
| Plan Check Approved | 8/12/2025 | MICHAEL LOPEZ |
| Issued | 8/14/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2023 | DAVID LOPEZ |
| Sewer availability | Cleared | 12/6/2023 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 1/19/2024 | JOHN CONNEALLY |
| Fire Marshal Fire Life Safety | Cleared | 2/21/2024 | FIRE DEPARTMENT |
| Green Code | Cleared | 8/26/2024 | MICHAEL LOPEZ |
| CPC | Cleared | 1/28/2025 | JACQUELINE TORRES |
| ZA Case | Cleared | 1/28/2025 | JACQUELINE TORRES |
| Low Impact Development (LID) | Cleared | 5/20/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 5/28/2025 | JEREMY CHOK |
| Zoning Plan Check | Cleared | 6/9/2025 | MICHAEL LOPEZ |
| DAS Clearance | Cleared | 6/13/2025 | MICHAEL LOPEZ |
Contact Information
| Contractor | Yireh Construction Inc; Lic. No.: 1089955-B | 16108 COMPASS AVE CHINO, CA 91708 |
| Engineer | Kim,, Seung; Lic. No.: S5909 | 9934 CEDAR CT CYPRESS, CA 90630 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/20/2025 | Approved | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 9/18/2025 | Partial Approval | MARTIN TAVITIAN |
| METHANE-Barrier | 9/18/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Subgrade | 9/18/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 9/19/2025 | Partial Approval | MARTIN TAVITIAN |
| METHANE-Barrier | 9/19/2025 | Partial Approval | MARTIN TAVITIAN |
| METHANE-Subgrade | 9/19/2025 | Approved | MARTIN TAVITIAN |
| Pre-Inspection | 10/16/2025 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 10/20/2025 | Partial Approval | MARTIN TAVITIAN |
| METHANE-Barrier | 10/20/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Special/Order Compliance | 10/20/2025 | Corrections Issued | MARTIN TAVITIAN |
| Green Building Rough | 10/31/2025 | Approved | MARTIN TAVITIAN |
| METHANE-Rough | 10/31/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 10/31/2025 | Partial Inspection | MARTIN TAVITIAN |
| METHANE-Rough | 11/12/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 11/12/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 11/19/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Rough | 11/19/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Pre-Inspection | 11/20/2025 | Partial Approval | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 11/24/2025 | Partial Approval | MARTIN TAVITIAN |
| METHANE-Rough | 12/2/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 12/2/2025 | Corrections Issued | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 12/4/2025 | Approved | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 12/4/2025 | Partial Approval | MARTIN TAVITIAN |
| METHANE-Barrier | 12/4/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 12/5/2025 | Corrections Issued | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 12/8/2025 | Corrections Issued | RONALD JIMENEZ |
| Footing/Foundation/Slab | 12/8/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| METHANE-Barrier | 12/8/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Special/Order Compliance | 12/8/2025 | Partial Inspection | REGINA MENDEZ |
| Excavation/Setback/Form/Re-Bar | 12/17/2025 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 12/17/2025 | Partial Approval | MARTIN TAVITIAN |
| METHANE-Barrier | 12/17/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Rough | 12/30/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Special/Order Compliance | 12/30/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 12/30/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Pre-Inspection | 12/31/2025 | Approved | MARTIN TAVITIAN |
| Special/Order Compliance | 12/31/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Rough | 1/2/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Special/Order Compliance | 1/2/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 1/2/2026 | Partial Approval | MARTIN TAVITIAN |
| Pre-Inspection | 1/5/2026 | Partial Approval | MARTIN TAVITIAN |
| Pre-Inspection | 1/7/2026 | Approved | MARTIN TAVITIAN |
| METHANE-Rough | 1/13/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 1/13/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Rough | 1/16/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 1/16/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Light Gage Steel Frame | 2/10/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Light Gage Steel Frame | 2/13/2026 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 2/18/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Rough | 2/18/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Rough | 2/19/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Deputy Methane Barrier | 2/20/2026 | No Access for Inspection | MARTIN TAVITIAN |
| METHANE-Barrier | 2/20/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Insulation | 2/24/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Interior/Exterior Lathing | 2/24/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Insulation | 2/25/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Light Gage Steel Frame | 2/25/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Insulation | 2/27/2026 | Conditional Approval | CHRISTOPHER BLACKWOOD |
| Interior/Exterior Lathing | 2/27/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Light Gage Steel Frame | 2/27/2026 | Conditional Approval | CHRISTOPHER BLACKWOOD |
| Insulation | 3/3/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Light Gage Steel Frame | 3/3/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Insulation | 3/4/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Light Gage Steel Frame | 3/4/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Insulation | 3/10/2026 | Partial Approval | IAN BLINN |
| Interior/Exterior Lathing | 3/10/2026 | Partial Approval | IAN BLINN |
| Excavation/Setback/Form/Re-Bar | 3/13/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 3/13/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Barrier | 3/13/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Deputy Methane Barrier | 3/17/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 3/17/2026 | Approved | DARRYL ARNOLD |
| METHANE-Barrier | 3/17/2026 | Partial Inspection | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 3/19/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| METHANE-Barrier | 3/19/2026 | Approved | CHRISTOPHER BLACKWOOD |
| Insulation | 3/20/2026 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 3/21/2026 | Off-Hour Fees Due | |
| Drywall Nailing | 3/23/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 3/23/2026 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 3/25/2026 | Partial Approval | ALFREDO LOPEZ |