3521 1/2 W 59TH ST 90043
Certificate Information: 3521 1/2 W 59TH ST 90043
- Application / Permit
- 23014-10000-04565
- Plan Check / Job No.
- B23LA21068
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF EXISTING GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION PER ORDINANCE
- Permit Issued
- Issued on 12/13/2023
- Issuing Office
- Current Status
- CofO Issued on 11/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2023 | MINA HABILI |
| Corrections Issued | 11/8/2023 | MINA HABILI |
| Building Plans Picked Up | 11/9/2023 | APPLICANT |
| Applicant returned to address corrections | 12/8/2023 | MINA HABILI |
| Plan Check Approved | 12/13/2023 | MINA HABILI |
| Issued | 12/13/2023 | APPLICANT |
| CofO in Progress | 11/8/2024 | AMIR NAZARIAN |
| Permit Finaled | 11/10/2024 | DEROLD HAUFF |
| CofO Issued | 11/10/2024 | DEROLD HAUFF |
| Permit Finaled | 11/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 11/13/2023 | HUGO GARRIDO GARZA |
| Address approval | Cleared | 11/27/2023 | ARNULFO CHAMU |
| Roof/Waste drainage to street | Cleared | 11/27/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 12/1/2023 | ARNULFO CHAMU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/1/2024 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/14/2024 | Approved | JOSE MACIAS |
| Deputy Drilled-In Anchors | 2/15/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 2/28/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 4/11/2024 | Not Ready for Inspection | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 6/24/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 6/24/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 6/24/2024 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 6/24/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 6/24/2024 | Corrections Issued | JOSE MACIAS |
| Sewer | 6/24/2024 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 6/25/2024 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 6/27/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 6/28/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 6/28/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 6/28/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/28/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 6/28/2024 | Approved | JOSE MACIAS |
| Insulation | 8/8/2024 | Conditional Approval | JOSH MEISTER |
| Drywall Nailing | 8/14/2024 | Corrections Issued | ALEX COLIN |
| Interior/Exterior Lathing | 9/23/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Shower Pan | 9/23/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 10/1/2024 | Partial Approval | ALEX COLIN |
| Final | 11/5/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 11/5/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Smoke Detectors | 11/5/2024 | Approved | AMIR NAZARIAN |
| Final | 11/7/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Green Building Final | 11/7/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Approved | AMIR NAZARIAN |