2201 W PASEO DEL MAR 90732

Certificate Information: 2201 W PASEO DEL MAR 90732

Application / Permit
23014-10000-04544
Plan Check / Job No.
B23LA20962
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: REMOVE AND REPLACE ATTACHED PATIO COVER WITH A (N) 16'-1" X 12'-7" ADDITION AND REMODEL TO (E) ONE-STORY SINGLE-FAMILY DWELLING - PER ENGINEER
Permit Issued
Issued on 5/31/2024
Issuing Office
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 ALEC MOUSAKHANIAN
Corrections Issued 11/11/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 2/15/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 3/26/2024 ALFRED RAMIREZ
Applicant returned to address corrections 3/29/2024 ALFRED RAMIREZ
Plan Check Approved 5/16/2024 ALFRED RAMIREZ
Issued 5/31/2024 APPLICANT
CofO in Progress 7/22/2025 JOSEPH MCGARRY
Permit Finaled 7/22/2025 ANSON MAGLASANG
CofO Issued 7/22/2025 ANSON MAGLASANG
Permit Finaled 7/22/2025 ANSON MAGLASANG

Permit Application Clearance Information

Specific Plan Cleared 12/11/2023 JOE TAM
Eng Process Fee Ord 176,300 Cleared 3/21/2024 JILVER MAZARIEGOS
Roof/Waste drainage to street Cleared 3/21/2024 JILVER MAZARIEGOS
Coastal Zone Cleared 3/29/2024 ROSALINDA MEZA
Grading Pre-Inspection Cleared 5/16/2024 ALEC MOUSAKHANIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/3/2024 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 10/7/2024 Corrections Issued JOSEPH MCGARRY
METHANE-Barrier 10/7/2024 Approved JOSEPH MCGARRY
METHANE-Subgrade 10/7/2024 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 10/9/2024 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 10/25/2024 Conditional Approval BEN MOLSTAD
Footing/Foundation/Slab 10/28/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 11/8/2024 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 11/8/2024 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 2/20/2025 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Approved JOSEPH MCGARRY
METHANE-Rough 2/20/2025 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 2/20/2025 Approved JOSEPH MCGARRY
Insulation 2/25/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 2/25/2025 Approved JOSEPH MCGARRY
Drywall Nailing 3/5/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 3/5/2025 Partial Approval JOSEPH MCGARRY
Shower Pan 3/5/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 3/7/2025 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 3/28/2025 Approved JOSEPH MCGARRY
ELECTRICAL-Final 7/21/2025 Approved JOSEPH MCGARRY
Final 7/21/2025 OK to Issue CofO JOSEPH MCGARRY
HVAC-Final 7/21/2025 Approved JOSEPH MCGARRY
PLUMBING-Final 7/21/2025 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/21/2025 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 7/21/2025 Approved JOSEPH MCGARRY