204 N MANHATTAN PL 1-17 90004

Certificate Information: 204 N MANHATTAN PL 1-17 90004

Application / Permit
23014-10000-04534
Plan Check / Job No.
B23LA20911
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
eplanGarage conversion into 3 ADU's
Permit Issued
Issued on 4/27/2024
Issuing Office
Current Status
CofO Issued on 1/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 SALVADOR QUINTANILLA
Corrections Issued 11/18/2023 SALVADOR QUINTANILLA
Quality Review Completed 11/27/2023 PETER KIM
Assigned to Zoning Architect 12/1/2023 SALVADOR QUINTANILLA
Applicant returned to address corrections 1/2/2024 SALVADOR QUINTANILLA
Applicant returned to address corrections 2/5/2024 SALVADOR QUINTANILLA
Applicant returned to address corrections 2/12/2024 SALVADOR QUINTANILLA
Applicant returned to address corrections 2/13/2024 SALVADOR QUINTANILLA
Applicant returned to address corrections 3/1/2024 SALVADOR QUINTANILLA
Plan Check Approved 4/15/2024 SALVADOR QUINTANILLA
Issued 4/27/2024 APPLICANT
CofO Issued 1/9/2025 WINSTON DUNNING
Permit Finaled 1/9/2025 WINSTON DUNNING

Permit Application Clearance Information

Sewer availability Cleared 12/8/2023 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 12/12/2023 JUSTIN BICOL
Historic Resource Verification Cleared 12/21/2023 RAFAEL FONTES
Green Code Cleared 1/10/2024 Luke Gonzales
Address approval Cleared 1/17/2024 DAVID LOPEZ
Redevelopment Project Area Cleared 2/29/2024 YASMINE BASHIRI
DAS Clearance Cleared 3/12/2024 Luke Gonzales
Zoning Plan Check Cleared 4/12/2024 Luke Gonzales

Contact Information

Contractor Stay Forever Construction Corporation; Lic. No.: 986055-B       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: NA87661       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2024 Approved MARTIN TAVITIAN
Footing/Foundation/Slab 6/6/2024 Partial Approval MARTIN TAVITIAN
Pre-Inspection 6/25/2024 Partial Approval JACOB MYERS
Green Building Rough 7/22/2024 Not Ready for Inspection JACOB MYERS
Interior/Exterior Lathing 7/22/2024 Approved JACOB MYERS
Wood Frame 7/22/2024 Partial Approval JACOB MYERS
Insulation 7/25/2024 Approved RONALD JIMENEZ
Drywall Nailing 7/30/2024 Approved JACOB MYERS
Interior/Exterior Lathing 8/28/2024 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 11/6/2024 SGSOV Not Ready CHRISTOPHER BLACKWOOD
Pre-Inspection 11/7/2024 Partial Approval MARTIN TAVITIAN
Protected Tree Letter 11/7/2024 Approved MARTIN TAVITIAN
Protected Tree Letter 11/7/2024 Partial Approval MARTIN TAVITIAN
Deputy Drilled-In Anchors 1/9/2025 Conditional Approval WINSTON DUNNING
Final 1/9/2025 Conditional Approval WINSTON DUNNING
Footing/Foundation/Slab 1/9/2025 Approved WINSTON DUNNING
Green Building Final 1/9/2025 Approved WINSTON DUNNING
Green Building Rough 1/9/2025 Approved WINSTON DUNNING
SGSOV-Seismic Gas S/O Valve 1/9/2025 SGSOV Approved WINSTON DUNNING
Smoke Detectors 1/9/2025 Approved WINSTON DUNNING
Wood Frame 1/9/2025 Approved WINSTON DUNNING