1456 W OAK GROVE DR 90041
Certificate Information: 1456 W OAK GROVE DR 90041
- Application / Permit
- 23014-10000-04514
- Plan Check / Job No.
- B23LA20827
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 2/28/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | DANIEL YIP |
| Corrections Issued | 11/21/2023 | DANIEL YIP |
| Quality Review Completed | 12/5/2023 | KEN GILL |
| Building Plans Picked Up | 12/11/2023 | APPLICANT |
| Applicant returned to address corrections | 1/19/2024 | DANIEL YIP |
| Plan Check Approved | 1/25/2024 | DANIEL YIP |
| Issued | 2/28/2024 | APPLICANT |
| CofO in Progress | 2/21/2025 | BRENDAN MORELLI |
| Permit Finaled | 2/23/2025 | DEROLD HAUFF |
| CofO Issued | 2/23/2025 | DEROLD HAUFF |
| Permit Finaled | 2/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/14/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 12/14/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2023 | JUSTIN BICOL |
| Excavation more than 5-ft deep | Cleared | 1/19/2024 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 1/19/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 1/19/2024 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 1/19/2024 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zlotnik,, Alexander; Lic. No.: C69417 | 11323 PASEO LA CUMBRE PORTER RANCH, CA 91326 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/8/2024 | Partial Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 4/25/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/22/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 5/23/2024 | Partial Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 5/24/2024 | Conditional Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 6/11/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Masonry Wall/Backfill | 7/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/9/2024 | Partial Approval | CRAIG VAUGHAN |
| Masonry Wall/Backfill | 7/9/2024 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/22/2024 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 7/22/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Reinf. Masonry | 7/23/2024 | Conditional Approval | CRAIG VAUGHAN |
| Masonry Wall/Backfill | 7/31/2024 | Partial Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 8/6/2024 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/12/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/12/2024 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/12/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 8/12/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/12/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/12/2024 | Approved | CRAIG VAUGHAN |
| Deputy Wood Construction | 8/13/2024 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/14/2024 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/14/2024 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/14/2024 | Approved | CRAIG VAUGHAN |
| Green Building Final | 8/14/2024 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 8/14/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 8/21/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 8/26/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/26/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/30/2024 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/23/2024 | Approved | BRENDAN MORELLI |
| Final | 12/23/2024 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 12/23/2024 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/2/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Final | 1/7/2025 | Partial Approval | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Approved | BRENDAN MORELLI |
| Final | 1/14/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Gas Test | 1/14/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 2/3/2025 | OK to Issue CofO | BRENDAN MORELLI |
| Gas Test | 2/3/2025 | Approved | BRENDAN MORELLI |