1456 W OAK GROVE DR 90041

Certificate Information: 1456 W OAK GROVE DR 90041

Application / Permit
23014-10000-04514
Plan Check / Job No.
B23LA20827
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 2/28/2024
Issuing Office
Metro
Current Status
CofO Issued on 2/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 DANIEL YIP
Corrections Issued 11/21/2023 DANIEL YIP
Quality Review Completed 12/5/2023 KEN GILL
Building Plans Picked Up 12/11/2023 APPLICANT
Applicant returned to address corrections 1/19/2024 DANIEL YIP
Plan Check Approved 1/25/2024 DANIEL YIP
Issued 2/28/2024 APPLICANT
CofO in Progress 2/21/2025 BRENDAN MORELLI
Permit Finaled 2/23/2025 DEROLD HAUFF
CofO Issued 2/23/2025 DEROLD HAUFF
Permit Finaled 2/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/14/2023 JUSTIN BICOL
Sewer availability Cleared 12/14/2023 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 12/18/2023 JUSTIN BICOL
Excavation more than 5-ft deep Cleared 1/19/2024 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/19/2024 CALOSHA APPROVED
GPI Written Notices Cleared 1/19/2024 DANIEL YIP
Grading Pre-Inspection Cleared 1/19/2024 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,
Engineer Zlotnik,, Alexander; Lic. No.: C69417 11323 PASEO LA CUMBRE      PORTER RANCH, CA 91326

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2024 Partial Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 4/25/2024 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 5/22/2024 Not Ready for Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 5/23/2024 Partial Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 5/24/2024 Conditional Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 6/11/2024 Conditional Approval ALIZAH MAYAGOITIA
Masonry Wall/Backfill 7/8/2024 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 7/9/2024 Partial Approval CRAIG VAUGHAN
Masonry Wall/Backfill 7/9/2024 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 7/22/2024 Partial Approval CRAIG VAUGHAN
Green Building Rough 7/22/2024 Not Ready for Inspection CRAIG VAUGHAN
Deputy Reinf. Masonry 7/23/2024 Conditional Approval CRAIG VAUGHAN
Masonry Wall/Backfill 7/31/2024 Partial Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 8/6/2024 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 8/12/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 8/12/2024 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 8/12/2024 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 8/12/2024 Approved CRAIG VAUGHAN
HVAC-Rough 8/12/2024 Approved CRAIG VAUGHAN
PLUMBING-Rough 8/12/2024 Approved CRAIG VAUGHAN
Deputy Wood Construction 8/13/2024 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 8/14/2024 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 8/14/2024 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/14/2024 Approved CRAIG VAUGHAN
Green Building Final 8/14/2024 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 8/14/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/21/2024 Partial Approval CRAIG VAUGHAN
Shower Pan 8/21/2024 Approved CRAIG VAUGHAN
Insulation 8/26/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/26/2024 Approved CRAIG VAUGHAN
Drywall Nailing 8/30/2024 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 12/23/2024 Approved BRENDAN MORELLI
Final 12/23/2024 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 12/23/2024 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 1/2/2025 SGSOV Not Ready BRENDAN MORELLI
Final 1/7/2025 Partial Approval BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Approved BRENDAN MORELLI
Final 1/14/2025 Not Ready for Inspection OSVALDO PARAMO
Gas Test 1/14/2025 Not Ready for Inspection OSVALDO PARAMO
Final 2/3/2025 OK to Issue CofO BRENDAN MORELLI
Gas Test 2/3/2025 Approved BRENDAN MORELLI