418 S ORANGE DR 90036

Certificate Information: 418 S ORANGE DR 90036

Application / Permit
23014-10000-04510
Plan Check / Job No.
B23LA20812
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Carport+Storage (165sqft) conversion and addition (172sqft) to Accessory Dwelling Unit (ADU) (337sqft) per state law
Permit Issued
Issued on 5/23/2024
Issuing Office
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2023 APPLICANT
Assigned to Plan Check Engineer 11/7/2023 KHUONG TRUONG
Corrections Issued 11/8/2023 KHUONG TRUONG
Plan Check Approved 3/27/2024 KHUONG TRUONG
Issued 5/23/2024 APPLICANT
CofO in Progress 7/14/2025 RONNIE MINDANAO
CofO Issued 7/16/2025 DEROLD HAUFF
Permit Finaled 7/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/16/2023 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 11/16/2023 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 11/16/2023 VLADIMIR ARUTYUNYAN
Construction near power lines Cleared 2/22/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/28/2024 VLADIMIR ARUTYUNYAN

Contact Information

Architect Sheinberg,, Roberto; Lic. No.: C39035 4209 SANTA MONICA BLVD #100      LOS ANGELES, CA 90029
Contractor Gallegos Juan M; Lic. No.: 872177-B       ,
Contractor Juan M Gallegos; Lic. No.: 872177-B       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/12/2024 Conditional Approval RICHARD DOCKUS
ELECTRICAL-Rough 6/13/2024 Approved ROY SPAULDING
Footing/Foundation/Slab 6/13/2024 Approved ROY SPAULDING
METHANE-Barrier 6/13/2024 Approved ROY SPAULDING
METHANE-Subgrade 6/13/2024 Approved ROY SPAULDING
PLUMBING-Rough 7/22/2024 Approved RONNIE MINDANAO
Underground Mechanical 7/22/2024 Corrections Issued RONNIE MINDANAO
Deputy Drilled-In Anchors 7/31/2024 Conditional Approval RONNIE MINDANAO
ELECTRICAL-Rough 7/31/2024 Approved RONNIE MINDANAO
Sewer 7/31/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Approved RONNIE MINDANAO
HVAC-Rough 8/8/2024 Not Ready for Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 9/13/2024 Not Ready for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Approved RONNIE MINDANAO
Green Building Rough 9/13/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 9/13/2024 Approved RONNIE MINDANAO
METHANE-Rough 9/13/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 10/15/2024 Approved JOSE MACIAS
Green Building Rough 10/15/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 10/15/2024 Approved JOSE MACIAS
Shower Pan 10/15/2024 Approved JOSE MACIAS
Insulation 10/22/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 10/22/2024 Not Ready for Inspection RONNIE MINDANAO
Drywall Nailing 10/28/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Approved RONNIE MINDANAO
Shower Pan 10/28/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 4/14/2025 Corrections Issued RONNIE MINDANAO
PLUMBING-Final 4/14/2025 Approved RONNIE MINDANAO
ELECTRICAL-Final 4/17/2025 Approved RONNIE MINDANAO
Final 4/17/2025 Corrections Issued RONNIE MINDANAO
Green Building Final 4/17/2025 Approved RONNIE MINDANAO
HVAC-Final 4/17/2025 Corrections Issued RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV No Gas RONNIE MINDANAO
Smoke Detectors 4/17/2025 Approved RONNIE MINDANAO
Final 4/25/2025 Corrections Issued RONNIE MINDANAO
HVAC-Final 4/25/2025 Approved RONNIE MINDANAO
Final 6/25/2025 Conditional Approval RONNIE MINDANAO
Final 7/11/2025 OK to Issue CofO RONNIE MINDANAO