7230 W 80TH ST 90045
Certificate Information: 7230 W 80TH ST 90045
- Application / Permit
- 23014-10000-04499
- Plan Check / Job No.
- B23LA20749
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Major remodeling to existing 1-story single family dwelling that consists of 24.7 sqft addition at first floor and 1107 sqft addition at second floor. NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 12/21/2023
- Issuing Office
- Current Status
- CofO Issued on 12/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | JAD BASMA |
| Corrections Issued | 11/12/2023 | JAD BASMA |
| Quality Review Completed | 11/17/2023 | GARO TELMI |
| Plan Check Approved | 12/20/2023 | JAD BASMA |
| Issued | 12/21/2023 | APPLICANT |
| CofO in Progress | 12/5/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 12/9/2024 | RICHARD STEINBACH |
| CofO Issued | 12/9/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/9/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2023 | DARIN LAM |
| Sewer availability | Cleared | 11/21/2023 | DARIN LAM |
| ZA Case | Cleared | 11/28/2023 | MAXFIELD VERMY |
| Low Impact Development (LID) | Cleared | 11/30/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 12/2/2023 | DARIN LAM |
Contact Information
| Contractor | A P Remodeling Inc; Lic. No.: 1049032-B | , |
| Contractor | Ap Remodeling Inc; Lic. No.: 1049032-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/18/2024 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 1/25/2024 | Conditional Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 1/30/2024 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 2/9/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2024 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 5/8/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 5/8/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 5/8/2024 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 5/9/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 5/9/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 5/9/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 5/14/2024 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 5/20/2024 | Approved | BOBBY KEY |
| Green Building Rough | 5/20/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 5/20/2024 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 5/20/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 5/28/2024 | Not Ready for Inspection | BOBBY KEY |
| Shower Pan | 5/28/2024 | Approved | BOBBY KEY |
| Insulation | 6/3/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Approved | BOBBY KEY |
| Insulation | 6/6/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 6/6/2024 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 6/10/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 6/14/2024 | Approved | HERBERT GIRON |
| Special/Order Compliance | 8/7/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 8/26/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 9/3/2024 | Conditional Approval | BOBBY KEY |
| Service/Power Release | 9/3/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/13/2024 | Not Ready for Inspection | BOBBY KEY |
| Final | 9/13/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 9/13/2024 | Approved | BOBBY KEY |
| Gas Test | 9/13/2024 | Approved | BOBBY KEY |
| Green Building Final | 9/13/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 9/13/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/13/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 9/13/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 10/9/2024 | Corrections Issued | BOBBY KEY |
| Final | 10/9/2024 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 10/9/2024 | Approved | BOBBY KEY |
| HVAC-Final | 10/9/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Final | 10/9/2024 | Corrections Issued | BOBBY KEY |
| Smoke Detectors | 10/9/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/15/2024 | Approved | BOBBY KEY |
| Final | 10/15/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 10/15/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 10/15/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/29/2024 | Approved | BOBBY KEY |
| Final | 10/29/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 10/29/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 10/29/2024 | Approved | BOBBY KEY |
| Final | 11/14/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Final | 11/14/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/4/2024 | Approved | TEMISTOCLES CAAL |
| Final | 12/4/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| HVAC-Final | 12/4/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 12/4/2024 | Approved | TEMISTOCLES CAAL |