3706 S NORTON AVE 90018
Certificate Information: 3706 S NORTON AVE 90018
- Application / Permit
- 23014-10000-04465
- Plan Check / Job No.
- B23LA20562
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Dettached garage at rear of the lot conversion and addition to create new Accessory Dwelling Unit per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/3/2024
- Issuing Office
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2023 | EDWIN ESPIN |
| Corrections Issued | 11/6/2023 | EDWIN ESPIN |
| Plan Check Approved | 5/1/2024 | EDWIN ESPIN |
| Issued | 5/3/2024 | APPLICANT |
| CofO in Progress | 11/18/2025 | LUIS CASTRO |
| Permit Finaled | 11/18/2025 | DEROLD HAUFF |
| CofO Issued | 11/18/2025 | DEROLD HAUFF |
| Permit Finaled | 11/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/8/2023 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 12/8/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 12/12/2023 | JUSTIN BICOL |
| Construction near power lines | Cleared | 4/8/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dia,, Gil Aroja; Lic. No.: C26172 | 532 E 222ND STREET CARSON, CA 90745 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/19/2024 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/7/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/13/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 8/15/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/15/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/21/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Wood Construction | 9/24/2024 | Conditional Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/29/2024 | Not Ready for Inspection | BARRY HACHE |
| Green Building Rough | 10/29/2024 | Corrections Issued | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 10/29/2024 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 11/13/2024 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 11/13/2024 | Approved | BARRY HACHE |
| Green Building Rough | 11/13/2024 | Approved | BARRY HACHE |
| HVAC-Rough | 11/13/2024 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 11/13/2024 | Approved | BARRY HACHE |
| PLUMBING-Rough | 11/13/2024 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 11/19/2024 | Approved | BARRY HACHE |
| Underground Mechanical | 11/19/2024 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 11/26/2024 | Approved | BARRY HACHE |
| Insulation | 11/26/2024 | Corrections Issued | BARRY HACHE |
| Drywall Nailing | 12/3/2024 | Approved | JOSH MEISTER |
| Insulation | 12/3/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 12/3/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 12/12/2024 | Approved | BARRY HACHE |
| Shower Pan | 12/12/2024 | Approved | BARRY HACHE |
| Final | 6/6/2025 | No Access for Inspection | LUIS CASTRO |
| Footing/Foundation/Slab | 6/6/2025 | No Access for Inspection | LUIS CASTRO |
| Green Building Final | 6/6/2025 | No Access for Inspection | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Not Ready | LUIS CASTRO |
| Smoke Detectors | 6/6/2025 | No Access for Inspection | LUIS CASTRO |
| Final | 7/7/2025 | No Access for Inspection | LUIS CASTRO |
| Footing/Foundation/Slab | 7/7/2025 | No Access for Inspection | LUIS CASTRO |
| Green Building Final | 7/7/2025 | No Access for Inspection | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Not Ready | LUIS CASTRO |
| Smoke Detectors | 7/7/2025 | No Access for Inspection | LUIS CASTRO |
| Final | 7/28/2025 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 7/28/2025 | Approved | LUIS CASTRO |
| Green Building Final | 7/28/2025 | Not Ready for Inspection | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 7/28/2025 | Approved | LUIS CASTRO |
| Final | 8/14/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 8/14/2025 | Approved | LUIS CASTRO |
| Final | 10/7/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Final | 11/14/2025 | Approved | LUIS CASTRO |
| Final | 11/14/2025 | OK to Issue CofO | LUIS CASTRO |
| HVAC-Final | 11/14/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 11/14/2025 | Approved | LUIS CASTRO |