6385 W 78TH ST 90045
Certificate Information: 6385 W 78TH ST 90045
- Application / Permit
- 23014-10000-04463
- Plan Check / Job No.
- B23LA20537
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION AND REMODEL TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/29/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | YOUNG KIM |
| Corrections Issued | 11/15/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 12/8/2023 | KEN GILL |
| Building Plans Picked Up | 12/11/2023 | APPLICANT |
| Applicant returned to address corrections | 4/25/2024 | YOUNG KIM |
| Plan Check Approved | 5/3/2024 | YOUNG KIM |
| Issued | 7/29/2024 | APPLICANT |
| CofO in Progress | 1/29/2026 | ANTHONY EGSON |
| Permit Finaled | 1/30/2026 | RICHARD STEINBACH |
| CofO Issued | 1/30/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/30/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/20/2023 | MOHAMMAD HASAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2024 | DINAH GARIN |
| Low Impact Development (LID) | Cleared | 4/19/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/19/2024 | VLADIMIR ARUTYUNYAN |
| GPI Written Notices | Cleared | 4/25/2024 | MICHAEL LOPEZ |
| Grading Pre-Inspection | Cleared | 4/25/2024 | MICHAEL LOPEZ |
Contact Information
| Contractor | Leigh Construction; Lic. No.: 782532-B | 6511 81ST LOS ANGELES, CA 90045 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/27/2024 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/6/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 11/22/2024 | Corrections Issued | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Partial Approval | MICHAEL ALLEN |
| Gas Test | 12/20/2024 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 12/20/2024 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 1/27/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 1/27/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 2/18/2025 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Rough | 2/18/2025 | Partial Approval | MICHAEL ALLEN |
| HVAC-Rough | 2/18/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 3/6/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 3/6/2025 | Partial Approval | MICHAEL ALLEN |
| Special/Order Compliance | 3/6/2025 | Partial Approval | RUBEN RIVAS |
| Insulation | 3/20/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 3/20/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Drywall Nailing | 4/17/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 5/22/2025 | Partial Approval | RUBEN RIVAS |
| Shower Pan | 5/22/2025 | Approved | RUBEN RIVAS |
| Gas Test | 9/10/2025 | Approved | RUBEN RIVAS |
| Underground Mechanical | 10/30/2025 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 1/16/2026 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/16/2026 | Corrections Issued | ANTHONY EGSON |
| Final | 1/16/2026 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/16/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 1/16/2026 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 1/16/2026 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 1/16/2026 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/28/2026 | Approved | ANTHONY EGSON |
| Final | 1/28/2026 | OK to Issue CofO | ANTHONY EGSON |
| HVAC-Final | 1/28/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 1/28/2026 | Approved | ANTHONY EGSON |