7812 S HINDRY AVE 90045

Certificate Information: 7812 S HINDRY AVE 90045

Application / Permit
23014-10000-04461
Plan Check / Job No.
B23LA20533
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: MAJOR REMODEL TO (E) SFD INLCUDING NEW ROOF FRAMING, NEW FOUNDATION, AND NEW SLABS ON GRADE. 69 SF ADDITION TO FRONT, 95 SF ADDITION TO (E) ATTACHED GARAGE, 1587 SF ADDITION TO REAR, 191 SF ADDITION OF ATTACHED TRELLIS PATIO COVER AT REAR OF (E) SFD. ALL WORK PER ENGINEERED DESIGN. INTERIOR REMODEL THROUGHOUT. " NFPA - 13D FIRE SPINKLERES REQUIRED THROUGH OUT"
Permit Issued
Issued on 12/13/2023
Issuing Office
Current Status
CofO Issued on 8/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2023 APPLICANT
Assigned to Plan Check Engineer 11/1/2023 OMAR GARNICA
Corrections Issued 11/2/2023 OMAR GARNICA
Applicant returned to address corrections 11/28/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/2/2023 LUISANGEL VALENZUELA
Plan Check Approved 12/12/2023 LUISANGEL VALENZUELA
Issued 12/13/2023 APPLICANT
CofO in Progress 8/27/2024 BOBBY KEY
Permit Finaled 8/27/2024 RICHARD STEINBACH
CofO Issued 8/27/2024 RICHARD STEINBACH
Permit Finaled 8/27/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/6/2023 SERGIO VALENZUELA
Specific Plan Cleared 11/7/2023 ALESSANDRO MERCURI
GPI Written Notices Cleared 11/21/2023 OMAR GARNICA
Eng Process Fee Ord 176,300 Cleared 11/27/2023 DARIN LAM
Low Impact Development (LID) Cleared 11/27/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 11/27/2023 DARIN LAM
Sewer availability Cleared 11/27/2023 DARIN LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Ananian,, Vatche; Lic. No.: NA79073       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/5/2024 Partial Approval BOBBY KEY
Deputy Drilled-In Anchors 1/11/2024 Conditional Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 1/11/2024 Approved BOBBY KEY
Footing/Foundation/Slab 1/11/2024 Approved BOBBY KEY
Deputy Reinf. Concrete 1/17/2024 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Partial Approval BOBBY KEY
Deputy Wood Construction 2/21/2024 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 2/23/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 2/23/2024 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Not Ready for Inspection BOBBY KEY
HVAC-Rough 2/23/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 2/23/2024 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 2/28/2024 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Conditional Approval BOBBY KEY
HVAC-Rough 2/28/2024 Conditional Approval BOBBY KEY
PLUMBING-Rough 2/28/2024 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 3/11/2024 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 3/11/2024 Partial Approval BOBBY KEY
Rough-Elec/Plmb/HVAC 3/11/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 3/18/2024 Approved BOBBY KEY
Green Building Rough 3/18/2024 Approved BOBBY KEY
Interior/Exterior Lathing 3/18/2024 Approved BOBBY KEY
MERV13>=Rough 3/18/2024 Approved BOBBY KEY
Verify Sprinkler Sign Off 3/18/2024 Approved BOBBY KEY
Insulation 3/22/2024 Approved BOBBY KEY
Shower Pan 3/22/2024 Approved BOBBY KEY
Drywall Nailing 3/28/2024 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 3/28/2024 Approved BOBBY KEY
Drywall Nailing 4/1/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/19/2024 SGSOV Not Ready BOBBY KEY
Gas Test 7/26/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV Approved BOBBY KEY
Final 8/9/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 8/9/2024 Approved TEMISTOCLES CAAL
MERV13>=Final 8/9/2024 Approved TEMISTOCLES CAAL
Smoke Detectors 8/9/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 8/15/2024 Approved TEMISTOCLES CAAL
HVAC-Final 8/15/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 8/15/2024 Approved TEMISTOCLES CAAL
Final 8/27/2024 OK to Issue CofO BOBBY KEY
Service/Power Release 8/27/2024 Approved BOBBY KEY