14631 W HARTSOOK ST 91403

Certificate Information: 14631 W HARTSOOK ST 91403

Application / Permit
23014-10000-04452
Plan Check / Job No.
B23LA20515
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 11'-0" x 40'-0" ADDITION AT REAR OF (E) SINGLE FAMILY DWELLING FOR A NEW BEDROOM, EXERCISE ROOM AND DINING ROOM AND INTERIOR REMODEL.
Permit Issued
Issued on 1/17/2024
Issuing Office
Current Status
CofO Issued on 7/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2023 APPLICANT
Assigned to Plan Check Engineer 11/2/2023 SARKIS HARABEDIAN
Corrections Issued 11/3/2023 SARKIS HARABEDIAN
Plan Check Approved 1/16/2024 OMAR GARNICA
Issued 1/17/2024 APPLICANT
CofO in Progress 7/12/2024 VINCENT HANLEY
CofO Issued 7/23/2024 RUBEN SALAS
Permit Finaled 7/23/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/8/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/9/2023 CARLOS RAMIREZ
Sewer availability Cleared 11/9/2023 CARLOS RAMIREZ

Contact Information

Architect Rieke,, Jonathan Eric; Lic. No.: NA39938       ,
Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/18/2024 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/21/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 3/21/2024 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/27/2024 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval THOMAS FINNILA
HVAC-Rough 4/25/2024 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval THOMAS FINNILA
HVAC-Rough 5/1/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 5/7/2024 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 5/7/2024 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 6/10/2024 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 6/17/2024 Approved JACK KARGODORIAN
Insulation 6/17/2024 Approved JACK KARGODORIAN
Drywall Nailing 6/21/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/21/2024 Approved DAVID ANDERSON
ELECTRICAL-Final 7/11/2024 Approved VINCENT HANLEY
Final 7/11/2024 OK to Issue CofO VINCENT HANLEY
Footing/Foundation/Slab 7/11/2024 Approved VINCENT HANLEY
HVAC-Final 7/11/2024 Approved VINCENT HANLEY
PLUMBING-Final 7/11/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 7/11/2024 Approved VINCENT HANLEY