4403 W 59TH ST 90043
Certificate Information: 4403 W 59TH ST 90043
- Application / Permit
- 23014-10000-04442
- Plan Check / Job No.
- B23LA20465
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERSION OF (E) 2-CAR GARAGE WITH ADDITION TO BECOME A TWO STORY ADU PER ORDINANCE LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/19/2024
- Issuing Office
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | JAD BASMA |
| Corrections Issued | 11/14/2023 | JAD BASMA |
| Quality Review Completed | 11/16/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/31/2024 | JAD BASMA |
| Applicant returned to address corrections | 6/27/2024 | JAD BASMA |
| Plan Check Approved | 7/9/2024 | JAD BASMA |
| Issued | 8/19/2024 | APPLICANT |
| CofO in Progress | 5/26/2026 | LUIS CASTRO |
| Permit Finaled | 5/28/2026 | DEROLD HAUFF |
| CofO Issued | 5/28/2026 | DEROLD HAUFF |
| Permit Finaled | 5/28/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/11/2024 | ROGELIO CORTES |
| Address approval | Cleared | 4/22/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 4/22/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 5/1/2024 | TREVOR QUAN |
| Construction near power lines | Cleared | 5/8/2024 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 6/27/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 6/27/2024 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Reith,, David Lee; Lic. No.: NA72122 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/10/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Barrier | 10/10/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Subgrade | 10/10/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 1/15/2025 | Partial Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2025 | Partial Approval | BARRY HACHE |
| PLUMBING-Rough | 1/21/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Partial Approval | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 2/27/2025 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 4/7/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 4/7/2025 | Partial Approval | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Partial Approval | WAYNE REGESTER |
| Gas Test | 4/7/2025 | Partial Approval | WAYNE REGESTER |
| Sewer | 4/7/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 5/5/2025 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 5/5/2025 | Partial Approval | BRENDAN MORELLI |
| HVAC-Rough | 5/15/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Rough | 6/2/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 6/2/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 6/2/2025 | Approved | WAYNE REGESTER |
| METHANE-Rough | 6/2/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 6/2/2025 | Approved | WAYNE REGESTER |
| Wood Frame | 6/2/2025 | Approved | WAYNE REGESTER |
| Insulation | 6/5/2025 | Partial Approval | ANTHONY RAMOS |
| Drywall Nailing | 6/13/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 7/15/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 8/13/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 8/13/2025 | Approved | WAYNE REGESTER |
| Final | 8/13/2025 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 8/13/2025 | Approved | WAYNE REGESTER |
| Green Building Final | 8/13/2025 | Approved | WAYNE REGESTER |
| HVAC-Final | 8/13/2025 | Approved | WAYNE REGESTER |
| METHANE-Barrier | 8/13/2025 | Approved | WAYNE REGESTER |
| METHANE-Subgrade | 8/13/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 8/13/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 8/13/2025 | Approved | WAYNE REGESTER |
| Final | 5/22/2026 | OK to Issue CofO | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Approved | LUIS CASTRO |