3326 W LONDON ST 90026
Certificate Information: 3326 W LONDON ST 90026
- Application / Permit
- 23014-10000-04422
- Plan Check / Job No.
- B23LA20377
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition of 387 SF and interior remodel of to existing 1-story single family dwelling with attached garage. All work per engineer. Existing patio cover (64 sf) to be enclosed "COMPLY WITH DEPARTMENT ORDER effective date 09/01/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" **ePLAN**
- Permit Issued
- Issued on 12/11/2023
- Issuing Office
- Current Status
- CofO Issued on 3/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2023 | VICTOR CHEN |
| Corrections Issued | 11/1/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 11/30/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 12/8/2023 | JOSEPH RAFOLS |
| Issued | 12/11/2023 | APPLICANT |
| Permit Finaled | 3/2/2026 | DANIEL SANCHEZ |
| CofO Issued | 3/2/2026 | DANIEL SANCHEZ |
| Permit Finaled | 3/2/2026 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2023 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 11/2/2023 | DAVID LOPEZ |
| ZI | Cleared | 11/2/2023 | JAZMIN ROQUE |
| Grading Pre-Inspection | Cleared | 11/8/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Rebuilt Homes Inc; Lic. No.: 1063540-B | , |
| Contractor | Rebuilt; Lic. No.: 1063540-B | , |
| Engineer | Saleh,, Zouheir Toufic; Lic. No.: C42881 | 1304 CORTE MALTERA COSTA MESA, CA 92626 |
| Engineer | Saleh,, Zouheir Toufic; Lic. No.: NA42881 | , |
Inspector Information
| RUBEN PEREZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT NILES, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK BEVELAQUA, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL SANCHEZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| COREY HUPP, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| EMIL OPFFER, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/23/2024 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/23/2024 | Corrections Issued | COREY HUPP |
| METHANE-Barrier | 1/23/2024 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 1/23/2024 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/26/2024 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 2/8/2024 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 2/15/2024 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 3/26/2024 | Not Ready for Inspection | COREY HUPP |
| HVAC-Rough | 3/26/2024 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 3/26/2024 | Corrections Issued | COREY HUPP |
| Wood Frame | 3/26/2024 | Corrections Issued | COREY HUPP |
| ELECTRICAL-Rough | 4/4/2024 | Approved | COREY HUPP |
| HVAC-Rough | 4/4/2024 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 4/4/2024 | Partial Approval | COREY HUPP |
| Wood Frame | 4/4/2024 | Partial Approval | COREY HUPP |
| HVAC-Rough | 4/8/2024 | Not Ready for Inspection | COREY HUPP |
| HVAC-Rough | 4/11/2024 | Partial Approval | COREY HUPP |
| Interior/Exterior Lathing | 4/17/2024 | Approved | COREY HUPP |
| Shower Pan | 4/17/2024 | Approved | COREY HUPP |
| Insulation | 5/9/2024 | Partial Approval | COREY HUPP |
| Insulation | 5/16/2024 | Approved | EMIL OPFFER |
| Drywall Nailing | 5/24/2024 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 9/4/2024 | Not Ready for Inspection | EMIL OPFFER |
| Final | 9/4/2024 | Not Ready for Inspection | EMIL OPFFER |
| MERV13>=Final | 9/4/2024 | Not Ready for Inspection | EMIL OPFFER |
| MERV13>=Rough | 9/4/2024 | Not Ready for Inspection | EMIL OPFFER |
| METHANE-Final | 9/4/2024 | Not Ready for Inspection | EMIL OPFFER |
| METHANE-Rough | 9/4/2024 | Not Ready for Inspection | EMIL OPFFER |
| SGSOV-Seismic Gas S/O Valve | 9/4/2024 | SGSOV Not Ready | EMIL OPFFER |
| Smoke Detectors | 9/4/2024 | Approved | EMIL OPFFER |
| BUILDING-Rough-Frame | 9/6/2024 | Not Ready for Inspection | EMIL OPFFER |
| Final | 9/6/2024 | Not Ready for Inspection | EMIL OPFFER |
| MERV13>=Final | 9/6/2024 | Not Ready for Inspection | EMIL OPFFER |
| MERV13>=Rough | 9/6/2024 | Corrections Issued | EMIL OPFFER |
| METHANE-Final | 9/6/2024 | Approved | EMIL OPFFER |
| METHANE-Rough | 9/6/2024 | Approved | EMIL OPFFER |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | EMIL OPFFER |
| BUILDING-Rough-Frame | 9/30/2024 | Not Ready for Inspection | ROBERT NILES |
| Final | 9/30/2024 | Corrections Issued | ROBERT NILES |
| MERV13>=Final | 9/30/2024 | Not Ready for Inspection | ROBERT NILES |
| MERV13>=Rough | 9/30/2024 | Not Ready for Inspection | ROBERT NILES |
| SGSOV-Seismic Gas S/O Valve | 9/30/2024 | SGSOV Approved | ROBERT NILES |
| BUILDING-Rough-Frame | 12/3/2024 | Approved | EMIL OPFFER |
| Final | 12/3/2024 | Conditional Approval | EMIL OPFFER |
| MERV13>=Final | 12/3/2024 | Approved | EMIL OPFFER |
| MERV13>=Rough | 12/3/2024 | Approved | EMIL OPFFER |
| METHANE-Subgrade | 2/3/2026 | Approved | EMIL OPFFER |