6020 1/2 W COMEY AVE 90034
Certificate Information: 6020 1/2 W COMEY AVE 90034
- Application / Permit
- 23014-10000-04419
- Plan Check / Job No.
- B23LA20363
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan (e) Garage conversion to ADU with addition per Ordinance LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/12/2024
- Issuing Office
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | NEHEMIAS RAMOS |
| Corrections Issued | 11/12/2023 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 12/19/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 12/28/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 1/3/2024 | WEIJIAN HUANG |
| Plan Check Approved | 1/9/2024 | DANIEL YIP |
| Issued | 2/12/2024 | APPLICANT |
| CofO in Progress | 8/9/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 8/14/2024 | RICHARD STEINBACH |
| CofO Issued | 8/14/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/14/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2023 | ARNULFO CHAMU |
| Roof/Waste drainage to street | Cleared | 11/16/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 12/7/2023 | ARNULFO CHAMU |
| Tenant Habitability Plan | Cleared | 12/14/2023 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | O D Solutions Remodeling & Construction Inc; Lic. No.: 1105993-B | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/12/2024 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 4/10/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/10/2024 | Partial Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 4/12/2024 | Corrections Issued | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 4/16/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Underground Mechanical | 4/16/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/8/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Partial Approval | MEL KHACHATOURIAN |
| Gas Test | 5/8/2024 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 5/8/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| MERV13>=Rough | 5/8/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/8/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/15/2024 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 5/15/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/15/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/22/2024 | Partial Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/22/2024 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 5/28/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/28/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 5/28/2024 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 5/31/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 7/31/2024 | Approved | KIRK SANDERS |
| Final | 7/31/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 7/31/2024 | Approved | KIRK SANDERS |
| Green Building Final | 7/31/2024 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 7/31/2024 | Approved | KIRK SANDERS |
| MERV13>=Final | 7/31/2024 | Approved | KIRK SANDERS |
| MERV13>=Rough | 7/31/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 7/31/2024 | Approved | KIRK SANDERS |
| Final | 8/6/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 8/6/2024 | Approved | MEL KHACHATOURIAN |
| Final | 8/8/2024 | OK to Issue CofO | MEL KHACHATOURIAN |