9130 W HARGIS ST 90034
Certificate Information: 9130 W HARGIS ST 90034
- Application / Permit
- 23014-10000-04418
- Plan Check / Job No.
- B23LA20359
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF (N) IRREGULAR SHAPED 16'-0" x 20'-0" ENCLOSED NON-HABITABLE RECREATION ROOM TOO (E) S.F.D. PER IAPMO #0115
- Permit Issued
- Issued on 11/30/2023
- Issuing Office
- Current Status
- CofO Issued on 4/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2023 | HANS SANTIAGO |
| Corrections Issued | 10/30/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 11/2/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 11/9/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 11/17/2023 | DANIEL YIP |
| Applicant returned to address corrections | 11/22/2023 | PINANK PATEL |
| Plan Check Approved | 11/29/2023 | ALFRED RAMIREZ |
| Issued | 11/30/2023 | APPLICANT |
| CofO in Progress | 4/4/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 4/9/2024 | DANIEL ORRANTE |
| CofO Issued | 4/9/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/9/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/31/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2023 | ARNULFO CHAMU |
| Grading Pre-Inspection | Cleared | 11/14/2023 | ALEXANDER HELFER |
Contact Information
| Contractor | Higher Quality Construction; Lic. No.: 929362-B | , |
| Engineer | Cavanagh,, Terence; Lic. No.: S3107 | P O BOX 2059 FOLSOM, CA 957632059 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2024 | Approved | MEL KHACHATOURIAN |
| Pre-Inspection | 1/11/2024 | Approved | MEL KHACHATOURIAN |
| Special/Order Compliance | 2/27/2024 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 3/8/2024 | Partial Approval | MEL KHACHATOURIAN |
| Final | 3/8/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 3/8/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 3/8/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 3/8/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 3/8/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 3/15/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 3/15/2024 | Approved | MEL KHACHATOURIAN |