10599 N HASKELL AVE 91344

Certificate Information: 10599 N HASKELL AVE 91344

Application / Permit
23014-10000-04411
Plan Check / Job No.
B23LA20317
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing 1 story detached garage with addtion to ADU per engineer details (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 4/29/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2023 APPLICANT
Assigned to Plan Check Engineer 10/30/2023 AUNG SOE
Corrections Issued 11/3/2023 AUNG SOE
Building Plans Picked Up 11/8/2023 APPLICANT
Plan Check Approved 4/16/2024 ALEXANDER JOO
Issued 4/29/2024 APPLICANT
CofO in Progress 6/23/2025 CHRISTOPHER ROJAS
Permit Finaled 7/1/2025 RUBEN SALAS
Permit Finaled 7/1/2025 RUBEN SALAS
CofO Issued 7/1/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/4/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/13/2023 COLIN LOREDO
Sewer availability Cleared 11/13/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 3/29/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 4/5/2024 BRYAN GODINEZ

Contact Information

Contractor Dry Town Restoration & Construction; Lic. No.: 981859-B 904 E LOMITA AVE APT 5      GLENDALE, CA 91205
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/11/2024 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 6/25/2024 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 6/25/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 6/25/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/8/2024 Corrections Issued JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 8/8/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Approved JAVIER RAMOS JR
HVAC-Rough 8/8/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 8/8/2024 Approved JAVIER RAMOS JR
Sewer 8/8/2024 Approved JAVIER RAMOS JR
Underground Mechanical 8/8/2024 Partial Approval JAVIER RAMOS JR
Wood Frame 8/8/2024 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 8/14/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 8/14/2024 Approved JAVIER RAMOS JR
Green Building Rough 8/14/2024 Approved JAVIER RAMOS JR
Insulation 8/14/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/14/2024 Approved JAVIER RAMOS JR
Shower Pan 8/14/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 11/7/2024 Partial Inspection JAVIER RAMOS JR
Final 11/7/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 11/7/2024 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 11/7/2024 Approved JAVIER RAMOS JR
Final 5/12/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 5/12/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/12/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Final 6/10/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Approved CHRISTOPHER ROJAS
Final 6/18/2025 Partial Approval KEVIN BERBERYAN
Final 6/23/2025 OK to Issue CofO CHRISTOPHER ROJAS