907 E 118TH DR 90059
Certificate Information: 907 E 118TH DR 90059
- Application / Permit
- 23014-10000-04402
- Plan Check / Job No.
- B23LA20269
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 17'-5" X 13'-10" ADDITION TO EXISTING SINGLE FAMILY DWELLING TO CREATE MASTER BEDROOM, BATHROOM AND WALK-IN CLOSET. **SEECOMMENTS**
- Permit Issued
- Issued on 12/21/2023
- Issuing Office
- Current Status
- CofO Issued on 7/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 11/6/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 12/18/2023 | ALEC MOUSAKHANIAN |
| Issued | 12/21/2023 | APPLICANT |
| CofO in Progress | 7/19/2025 | MICHAEL PELHAM |
| Permit Finaled | 7/19/2025 | RICHARD STEINBACH |
| CofO Issued | 7/19/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/19/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/28/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2023 | WALLIE JONG |
| Sewer availability | Cleared | 12/18/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mendoza,, Fabian; Lic. No.: C90183 | PO BOX 2305 NORWALK, CA 90651 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/27/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/16/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 1/16/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Partial Approval | JAMES CHAVEZ |
| MERV13>=Rough | 1/16/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 1/16/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Sewer | 1/16/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 1/17/2024 | Conditional Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 1/22/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 1/22/2024 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 1/22/2024 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 1/22/2024 | Approved | JAMES CHAVEZ |
| Insulation | 1/25/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 1/25/2024 | Partial Approval | JAMES CHAVEZ |
| Drywall Nailing | 1/31/2024 | Approved | JOHN KLARIN |
| Drywall Nailing | 2/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 2/8/2024 | Partial Approval | BEN MOLSTAD |
| Final | 3/22/2024 | Corrections Issued | BEN MOLSTAD |
| MERV13>=Final | 3/22/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 3/22/2024 | Approved | BEN MOLSTAD |
| Final | 3/29/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Approved | BEN MOLSTAD |
| Final | 7/19/2025 | OK to Issue CofO | MICHAEL PELHAM |