403 E 57TH ST 90011

Certificate Information: 403 E 57TH ST 90011

Application / Permit
23014-10000-04391
Plan Check / Job No.
B23LA20238
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Addition to existing apartment and repair fire damaged roof. All work done per an engineered design.
Permit Issued
Issued on 1/23/2024
Issuing Office
Metro
Current Status
Issued on 1/23/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/25/2023 APPLICANT
Assigned to Plan Check Engineer 10/30/2023 LAWRENCE QUIRANTE
Corrections Issued 10/31/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 11/3/2023 APPLICANT
Plan Check Approved 12/26/2023 DANIEL SMILEY
Issued 1/23/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/8/2023 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 11/13/2023 ARNULFO CHAMU
Tenant Habitability Plan Cleared 12/19/2023 RICARDO BOHORQUEZ
Community Plan Implem. Overlay Cleared 12/26/2023 HELEN JADALI

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Approved DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 5/8/2024 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 5/8/2024 Not Ready for Inspection ALFREDO LOPEZ
Green Building Rough 5/8/2024 Not Ready for Inspection ALFREDO LOPEZ
Insulation 5/8/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 5/8/2024 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 5/14/2024 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 6/4/2024 Partial Approval ALFREDO LOPEZ
Wood Frame 6/4/2024 Not Ready for Inspection ALFREDO LOPEZ
Green Building Rough 6/24/2024 Partial Approval ALFREDO LOPEZ
Wood Frame 6/24/2024 Partial Approval ALFREDO LOPEZ
Green Building Rough 7/23/2024 Conditional Approval DARRYL ARNOLD
Insulation 7/23/2024 Approved DARRYL ARNOLD
Wood Frame 7/23/2024 Conditional Approval DARRYL ARNOLD
Drywall Nailing 8/5/2024 Corrections Issued DARRYL ARNOLD
Interior/Exterior Lathing 11/14/2024 Approved ALFREDO LOPEZ
Final 11/25/2024 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 11/25/2024 Approved ALFREDO LOPEZ
Green Building Final 11/25/2024 Approved ALFREDO LOPEZ
Green Building Rough 11/25/2024 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 11/25/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 11/25/2024 Approved ALFREDO LOPEZ
Final 2/13/2025 Conditional Approval ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 2/13/2025 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 2/13/2025 Approved ALFREDO LOPEZ